Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • FRD produces Fx Series scaling breakers for tunnel construction
    February 8, 2013
    Furukawa Rock Drill (FRD) has developed the Fx Series of small hydraulic breakers with a scaling version for tunnel use. Using a mono-block cylinder with replaceable wear parts, the Fx Series breakers are said to provide increased power with reduced operating noise. There are four Fx models available with weights of 112-300kg, they are intended for excavators with operating weights of 1.5-7 tonnes.
  • Cifa’s concrete leading position in world market
    January 6, 2017
    Cifa is among the leading worldwide manufacturers of concrete machinery and equipment. The company, under the China-based Zoomlion ownership since 2008, has sales and after-sales networks on all continents. In addition to its range of reliable, high-quality products, Cifa also offers customers financial support through Zoomlion Capital Financial Services.
  • Cifa’s concrete leading position in world market
    March 27, 2013
    Cifa is among the leading worldwide manufacturers of concrete machinery and equipment. The company, under the China-based Zoomlion ownership since 2008, has sales and after-sales networks on all continents. In addition to its range of reliable, high-quality products, Cifa also offers customers financial support through Zoomlion Capital Financial Services.
  • Doka chalks up sales revenue success
    January 6, 2017
    Globally renowned Austrian formwork company Doka has almost tripled its sales revenue in the last 12 years and is aiming for greater success in 2013, according to Group chairman Josef Kurzmann. Kurzmann said the firm recorded sales revenue of €853million in 2012, compared to €326million in 2000. Additionally, the percentage of non-European sales revenue accrued by Doka had increased from 6% in 2000 to 42% in 2012. To achieve further sales revenue growth, Kurzmann said Latin America, North America and India