Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Systra, Kiewit and Hatch to build third bridge in Kingston, Canada
    August 31, 2018
    Kingston, Canada, has selected Systra International Bridge Technologies, Peter Kiewit Sons and Hatch as the preferred consortium for the design and build Third Crossing project. Seven international teams answered the requests for proposals in February and 2018 with Systra, Kiewit and Hatch eventually chosen from a shortlist of three groups. The consortium will use an integrated project delivery model for the two-lane 1.2km bridge with a pedestrian and cycle path over the Cataraqui River will connect
  • Nice in 2018: The Pavement Preservation & Recycling Summit (PPRS)
    November 17, 2017
    Siobhan McKelvey, president of the Paris-based International Bitumen Emulsion Federation (IBEF), explains the importance for attending next year’s Pavement Preservation & Recycling Summit. The event will be held in Nice in southern France from 26-28 March at the Nice Acropolis. One of the highlights for me that is provided by the PPRS platform is the opportunity to exchange on communication experiences throughout the world and how the challenges of promoting the role of a good road network are met.
  • Melbourne link: Hyder and Parsons Brinckerhoff to be design team
    October 22, 2014
    Hyder and Parsons Brinckerhoff have been appointed as the design team for the US$5.97 billion East West Link in Melbourne, Australia. The two engineering and management consultancies are in a 50/50 joint venture to provide detailed design and construction support services for the 6.6km Stage 1 work, which is the eastern section, of the project. Together with the proposed western section, the completed East West Link will cost around $7 billion. The toll road will form an 18km cross-city connection ext
  • NDT sensor fusion in structural pavement condition surveys
    February 27, 2017
    Early detection of pavement defects and the causes of deterioration is essential for effective maintenance planning, writes Dr Alena Uus* There is a need for optimisation and development of UK highway survey methods that would provide comprehensive information on the surface and subsurface pavement condition and operate at traffic speed, which eliminates the requirement for lane closures. Performance of non-destructive testing (NDT) methods commonly employed in pavement condition surveys can be potent