Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • High mobility is claimed for CIFA’s concrete plant
    February 7, 2013
    High mobility is claimed for CIFA’s mobile concrete batching plant, the CIFAMOBILE 50. “This is the first ever CIFA concrete batching plant we’ve built. It’s highly mobile and can be transported on wheels,” said Marco Brambati, director of marketing and business planning at the firm. The machine features a mixer that can produce 1/3 of concrete/cycle. This DNA 1.0 mixer is the smallest in the CIFA range (while the largest has a 3m3 capacity) and can deliver up to 50m3/hour of ready-mixed concrete. The plant
  • Goldhofer rescues O&K RH 120-E from Calenturitas de Prodeco Mine
    November 1, 2016
    It was reportedly a logistical challenge to collect a massive front shovel excavator from the open pit coal mine Calenturitas de Prodeco in north-eastern Colombia. The twin engines of the 290-tonne O&K RH 120-E mining excavator had given up the ghost and could not be repaired on site, leaving the monster stranded atop a high mound of earth. So the mining company contracted heavy haulage specialist Boom Logistics to collect the excavator and transport it to the repair shop 22km away. http://www.goldho
  • England’s A14 project River Great Ouse Viaduct completed
    February 28, 2019
    Construction of the biggest bridge in Highways England’s €1.73 billion A14 Cambridge-to-Huntingdon upgrade has been completed. The River Great Ouse Viaduct stretches for 0.8km and when opened to traffic next year will take the new A14 road over the floodplain and the East Coast Mainline Railway line. Work began in November 2016 on the bridge that is part of a new 27.4km bypass under construction to the south of Huntingdon and away from the existing A14. The road is being widened to three lanes in both
  • Liebherr 150EC-B is latest flat-top crane
    February 7, 2013
    Liebherr will show a modular design flat-top tower crane in the 150EC-B at this year’s Bauma. The 150EC-B is available in FR.tronic, with traditional contractor controls, or Litronic version with programmable logic controls. The flat-top crane can be had in 6 tonne and 8 tonne versions, with a maximum hook height of 63m and maximum working radius of 60m. Lift capacity at full radius is 1,700kg.