Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Outset’s Lanx Evo app turns an iPhone into a portable weigh scale display
    April 19, 2013
    Italian firm Outset has extended the functionality of its Lanx Evo on-board truck weighing system with the development of an app for the iOS platform. Called Lanx Evo, the app allows operators to use an iPhone to connect to Outset’s on-board truck scale, enabling the iOS device to show a continuous display of payload. This system is ideal, said the company, for truck drivers who load their own vehicles as the use of an iPhone gives them a portable weigh scale display that can be seen from the cab of the loa
  • Getech’s versatile sludge treatment solution
    April 5, 2013
    Due to an innovative and strong frame design and the use of premium raw materials and components, Getech/Gennaretti centrifuges can be employed across mining, tunnelling, petroleum and chemical industry-based sludge treatment processes. They can also be built in mobile plants on containers, easy to transport to remote areas and quick to install, able to manage sludge volumes going from 5 to 150m³ per hour.
  • First public outing for Liebherr tower crane at INTERMAT
    January 6, 2017
    Liebherr used INTERMAT 2012 to show its new 380 EC-B 16 Litronic flat-top crane. The 380tonne unit tops the 15-model range, which starts from 50tonnes. The new “flagship” can lift loads of up to 3,400kg at its 75m maximum radius. With the Litronic system, the 380 EC-B 16 can provide up to 20% more load lift at the push of a button. This is achieved by integrating the load-moment limiting system, the ABB operating-range limiting system and the MDA machine data evaluation program.
  • First public outing for Liebherr tower crane at INTERMAT
    April 20, 2012
    Liebherr used INTERMAT 2012 to show its new 380 EC-B 16 Litronic flat-top crane. The 380tonne unit tops the 15-model range, which starts from 50tonnes. The new “flagship” can lift loads of up to 3,400kg at its 75m maximum radius. With the Litronic system, the 380 EC-B 16 can provide up to 20% more load lift at the push of a button. This is achieved by integrating the load-moment limiting system, the ABB operating-range limiting system and the MDA machine data evaluation program.