Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Putzmeister adds five-section pump
    April 19, 2013
    Putzmeister has added a five-section 38m, 160m3/hr concrete pump, which can be used to place loads inside buildings some 3m higher than the four-section option. Built on a 26tonne chassis, the new 38.5 can reach heights of 31m while leaving the final boom section to pass inside the building. In common with the company’s other machines, the 38.5 now has outrigger sensing, which feeds into the control system and prevents the boom from extending/slewing if the outriggers are not fully deployed. The machine als
  • Percussive diamond inserts from Element Six lead to longer mining drill life
    January 6, 2017
    Synthetic diamond division of DeBeers, Element Six, has developed the 3D Percussive Diamond Insert (PDI) that it claims will radically cut costs in the mining drill industry. The 3D PDI uses the firm’s polycrystalline diamond technology to optimise wear and impact resistance properties, while improving penetration rates for the drill bit. The firm claims that tests of the drill insert show up to 10 times the drill life of a conventional tungsten carbide insert., greatly reducing costly rig downtime for serv
  • Percussive diamond inserts from Element Six lead to longer mining drill life
    February 7, 2013
    Synthetic diamond division of DeBeers, Element Six, has developed the 3D Percussive Diamond Insert (PDI) that it claims will radically cut costs in the mining drill industry. The 3D PDI uses the firm’s polycrystalline diamond technology to optimise wear and impact resistance properties, while improving penetration rates for the drill bit. The firm claims that tests of the drill insert show up to 10 times the drill life of a conventional tungsten carbide insert., greatly reducing costly rig downtime for serv
  • Kubota announces new Chinese diesel engine factory in Wuxi City
    January 6, 2017
    Japanese engine manufacturer Kubota will use Bauma to announce its plan to build another engine plant in Wuxi City, China for the production of vertical-shaft diesel engines. This facility has 18,000 m2 of manufacturing space and will be a fully-owned subsidiary of Kubota China Holdings Co. Production levels will reach 97,000 engines a year and operations start in 2014. Once opened, Kubota will have 6 manufacturing plants around the world for diesel engines.