Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Sleipner’s highlights system for moving excavators
    February 13, 2013
    Sleipner will explain the principle behind its “revolutionary method to improve the overall productivity in open-pit mines, quarries and construction sites.” The improvement is based on moving excavators around the site much faster than before, and additionally the Sleipner method saves time and money and considerably increases the excavators’ life, says the company.
  • A sinkhole in St Albans near London swallows up the road
    October 9, 2015
    Around 20 residents of St Albans, a town near London, were evacuated after a huge sinkhole appeared overnight. The hole, 20m in diameter and 10m deep, cut right across at the road and well into an adjoining garden, leaving one family’s car stranded on the driveway. Residents are said to have heard a crash before the huge crater appeared, according to a BBC report. The local fire service said it had been aware of a small hole that was due to be filled in, but a resident called the station at 1:30 in the mor
  • World debut for Ruthmann’s T 720 truck-mounted platform
    January 6, 2017
    The newest addition to Ruthmann’s Height series offers flexible access in awkward situations thanks to its extended telescoping upper boom with moveable jib. Ruthmann’s Steiger T 720 truck-mounted access platform made its world debut at bauma. The model has a working height of up to 72m and maximum lateral reach of 38m. Its design means that operators still have 21.4m reach at their disposal at a working height of 68m and with a 100kg cage load.
  • World debut for Ruthmann’s T 720 truck-mounted platform
    April 17, 2013
    The newest addition to Ruthmann’s Height series offers flexible access in awkward situations thanks to its extended telescoping upper boom with moveable jib. Ruthmann’s Steiger T 720 truck-mounted access platform made its world debut at bauma. The model has a working height of up to 72m and maximum lateral reach of 38m. Its design means that operators still have 21.4m reach at their disposal at a working height of 68m and with a 100kg cage load.