Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Ramtec adds new high-impact range of BH backhoe hydraulic hammers
    February 15, 2013
    Attachments specialist Ramtec is adding three new hydraulic hammers to its range at Bauma. The BH32, BH40 and BH52 backhoe hammers will be marketed under the Robi brand and the key features are high oil flows for high impact frequency, greater productivity levels and more penetration effort; constant blow energy to ensure constant strength; and low fuel consumption rates. All of the new backhoe hammers have sound suppression housing as standard, says Ramtec. The Finnish manufacturer will also unveil a new c
  • JCB emissions compliant engines to launch in wheeled loaders
    January 6, 2017
    JCB will launch 427 and 437 wheeled loaders at Bauma, powered by Stage IIIB/Tier 4 Interim Cummins engines. First seen in prototype form at last year’s Intermat show, the two loaders are powered by the Cummins QSB6.7 engine, which offers a 9.4% increase in torque over the previous model. This drives through a lock-up converter and customers can choose a standard four-speed or optional five-speed transmission, which delivers a 16% drop in fuel consumption. In-cab noise levels have been reduced to just 68dB(A
  • JCB emissions compliant engines to launch in wheeled loaders
    February 8, 2013
    JCB will launch 427 and 437 wheeled loaders at Bauma, powered by Stage IIIB/Tier 4 Interim Cummins engines. First seen in prototype form at last year’s Intermat show, the two loaders are powered by the Cummins QSB6.7 engine, which offers a 9.4% increase in torque over the previous model. This drives through a lock-up converter and customers can choose a standard four-speed or optional five-speed transmission, which delivers a 16% drop in fuel consumption. In-cab noise levels have been reduced to just 68dB(A
  • Deadline for submitting European Transport Conference 2014 abstracts
    February 3, 2014
    Tomorrow is the deadline for submitting abstracts to the European Transport Conference (ETC) 2014. The ETC connects the worlds of research, consultancy, policy and practice. Attendance at ETC allows different groups to pose questions to fellow professionals and to assess what is possible in terms of delivery. Researchers are challenged by policy-makers; practitioners need to deliver on the ground what the policy-makers want. The Association for European Transport has identified for the 2014 Conference so