Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • 3rd gala edition of Pilosio International Building the Peace Award at bauma
    April 9, 2013
    The construction industry’s social, contemporary and practical contribution to developing modern society and improving worldwide living conditions will be celebrated during bauma at the 3rd gala edition of the Pilosio International Building the Peace Award. The event, presented by renowned former CNN journalist Aleesio Vinci, will take place from 5pm on Wednesday April 17th 2013 at the Pilosio Stand (N 1020/1). The two previous editions in 2011 and 2012 drew guests from around the world from more than 20 c
  • Steering on drums: the Dynapac CG2300 roller
    February 13, 2013
    Having a long tradition of CG rollers, without central articulation, but with steering on drums, Atlas Copco’s Road Construction Equipment division now launches the Dynapac CG2300 asphalt roller. The roller is 3.95m long and 3m high with an inner turning radius of 3.1m. This means transportation advantages as well as ease of working in restricted areas.
  • Double delight for Powerscreen and DUO in Ghana
    January 6, 2017
    Powerscreen has signed DUO Africa as its first distributor in Ghana. And, as the ink dried on the contract at bauma, the company unveiled a deal to supply three crushing and screening trains. DUO Africa will sell equipment into Ghana and support Powerscreen products in the sub-Saharan region. Among its first contracts is to supply two Powerscreen XA400 primary jaw crushers, two 1000 Maxtrak cone crushers and two Chieftain 2100 triple-deck screens to UK-based Hawk Plant for a number of aggregate crushing ope
  • Double delight for Powerscreen and DUO in Ghana
    April 16, 2013
    Powerscreen has signed DUO Africa as its first distributor in Ghana. And, as the ink dried on the contract at bauma, the company unveiled a deal to supply three crushing and screening trains. DUO Africa will sell equipment into Ghana and support Powerscreen products in the sub-Saharan region. Among its first contracts is to supply two Powerscreen XA400 primary jaw crushers, two 1000 Maxtrak cone crushers and two Chieftain 2100 triple-deck screens to UK-based Hawk Plant for a number of aggregate crushing ope