Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Hamm is widening its line-up of new generation soil compactors
    January 6, 2017
    Hamm continues to develop its sophisticated soil compactor range with the addition of models aimed at the 11-16tonne weight classes. These are powered by Tier 4 Interim/Stage IIIB compliant diesels and share the same design concept as well as features and many components with the existing 18-15tonne rollers. The high compaction performance and unobstructed sight lines from the cab of the larger machines have also been carried over into the smaller units. The H11i, H13i and H16i compactors have 2.14m wide d
  • Hamm is widening its line-up of new generation soil compactors
    February 13, 2013
    Hamm continues to develop its sophisticated soil compactor range with the addition of models aimed at the 11-16tonne weight classes. These are powered by Tier 4 Interim/Stage IIIB compliant diesels and share the same design concept as well as features and many components with the existing 18-15tonne rollers. The high compaction performance and unobstructed sight lines from the cab of the larger machines have also been carried over into the smaller units. The H11i, H13i and H16i compactors have 2.14m wide d
  • IBTTA global summit 2014 takes a balanced view on sustainable transport
    October 8, 2014
    The upcoming International Bridge, Tunnel, and Turnpike Association (IBTTA) 2014 global summit in Prague, Czech Republic, will be focusing on “Sustainable Transport & Mobility for People and Goods” say the organisers with key sessions looking at “strategic issues such as interoperability (EETS/REETS), road safety, environmental protection, traffic in cities, big data, road user charging around the World and future developments, trends, and technologies.”
  • Lino Sella World has concrete presence in mixer market
    January 6, 2017
    Lino Sella World, the Italian concrete and mortar mixer manufacturer celebrating its 50th trading anniversary during 2013, exports worldwide while maintaining a strong Italian market presence. With a wide range of 140 to 500litre capacity mixers, Lino Sella World also produces hydraulic mixers with capacities from 520 up to 1500litres. The firm says all its machines are robust and made to a high standard with quality materials.