Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Shantui and Manitowoc agree joint venture to manufacture cranes in China
    January 6, 2017
    Manitowoc Cranes and Shantui Investment intend to form a new joint venture. This will build mobile cranes in China for both domestic and export markets. The name of the joint venture will be Shantui Manitowoc Crane Company, and it will commence operations once all relevant approvals are received. Within China, the cranes produced by the joint venture will be sold through Shantui’s vast domestic dealer network, in addition to Manitowoc’s own dealer network for truck cranes. The joint venture and this distrib
  • Shantui and Manitowoc agree joint venture to manufacture cranes in China
    January 28, 2013
    Manitowoc Cranes and Shantui Investment intend to form a new joint venture. This will build mobile cranes in China for both domestic and export markets. The name of the joint venture will be Shantui Manitowoc Crane Company, and it will commence operations once all relevant approvals are received. Within China, the cranes produced by the joint venture will be sold through Shantui’s vast domestic dealer network, in addition to Manitowoc’s own dealer network for truck cranes. The joint venture and this distrib
  • Sumitomo intends to boost its paver sales worldwide, as vice president international sales Ichiro Shimada explained
    January 6, 2017
    Sumitomo Construction Machinery intends to continue boosting export markets – a project that has been in hand for three years – according to vice president international sales Ichiro Shimada. “Sumitomo is dominant in Japan and we have 70% market share. But the market size is limited, maybe 400 units/year. We’re putting a lot of effort into the Chinese market,” said Shimada. Europe is another key market for Sumitomo and the firm is focussing on countries such as France, Poland and Switzerland, while it has a
  • Sumitomo intends to boost its paver sales worldwide, as vice president international sales Ichiro Shimada explained
    April 18, 2012
    Sumitomo Construction Machinery intends to continue boosting export markets – a project that has been in hand for three years – according to vice president international sales Ichiro Shimada. “Sumitomo is dominant in Japan and we have 70% market share. But the market size is limited, maybe 400 units/year. We’re putting a lot of effort into the Chinese market,” said Shimada. Europe is another key market for Sumitomo and the firm is focussing on countries such as France, Poland and Switzerland, while it has a