Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Massey Bridge concession popular
    October 10, 2016
    The concession package for the Massey Bridge in Canada is proving popular, with several firms keen to win the deal. Three consortia are in the running for the bridge project, which is intended to replace the existing George Massey Tunnel.
  • Automated testing is safer, cheaper and more thorough
    May 10, 2019
    New tests for cracking and rutting are easy to perform, use existing equipment and work well on mixes with different binders and recycled content - Kristina Smith writes Researchers at the Texas A&M Transportation Institute (TTI) have developed new tests for cracking and rutting, designed to be quick and easy to carry out, using existing laboratory equipment. The most advanced of these is the IDEAL Cracking Test (IDEAL-CT), which could be appearing in specifications in some of the US states in around six
  • Road sector drives Europe’s construction recovery
    September 13, 2017
    Despite political concerns and upheavals, Europe’s construction market is on the up, reports Graham Anderson Europe’s road building market is forecast to grow strongly in real terms up to 2019, as a strengthening economy boosts construction, creating investment and jobs. The market is predicted to grow by 16% between 2016 and 2019 and is being led by increases in the UK (39%), Norway (38%) and Poland (35%). In the UK, the market is buoyed by a number of major projects coming on stream, such as England’
  • VIDEO: Saskatoon’s Traffic Bridge demolished to make way for new bridge
    January 11, 2016
    A 100-year-old Parker truss bridge in western Canada had no official name until its 90th birthday, in 2007. Now, The Traffic Bridge – across the South Saskatchewan River in the city of Saskatoon - is no more, after its demolition earlier this month.

    The Traffic Bridge, nearly 6m wide and 290m long and took a year to build, and was Saskatoon’s first bridge across the river when it opened in 1907. The bridge was built by Winnipeg city-based John D. Gunn and Sons.