Skip to main content

Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Rebuilding a historic bridge linking the US and Canada
    March 8, 2016
    While many road authorities in North America are finding it difficult to stretch their bridge assets beyond half a century, one bridge is closing in on its centenary - David Arminas reports The international Peace Bridge, connecting the Canadian province of Ontario with the US state of New York, is 88 years young this year, and still going strong.
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Speed and precision make for perfect tunnelling combination
    May 21, 2014
    Speed and precision have been the hallmarks of a number of major road tunnelling projects across the globe over the last 12 months, as the latest sector equipment from leading manufacturers has found itself in high demand. Guy Woodford reports Herrenknecht tunnel boring machines (TBM) have been busy tunnelling under major Chinese rivers, demonstrating phenomenal speed, top safety levels and extreme precision while playing a key role in the construction of road tunnels in the Yangtze River Delta. The Yang
  • State of the art tunnel a conservation triumph
    May 2, 2012
    The opening of a 1.8km tunnel in southern England is designed to ease traffic bottlenecks in an environmentally sensitive area. Patrick Smith reports