Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Budapest’s Széchenyi Chain Bridge to reopen
    November 29, 2022
    The 380m-long suspension bridge in the Hungarian capital was built between 1839 and 1849 and was the first permanent bridge connecting the towns of Buda and Pest, lying on opposite banks of the Danube River.
  • Australia’s costly A$26 billion East Link Project
    February 5, 2025
    Australia’s East Link Project in Victoria will now cost as much as A$26 billion.
  • Fast flyover removal with specialist demolition equipment
    July 12, 2012
    An overcrowded Indian flyover was removed in record time using specialist demolition equipment, as Patrick Smith reports Demolition of the landmark Lalbaug flyover south of central Mumbai has been completed and work on a new bigger bridge has started in India's largest city. Although the 38-year-old Sant Dnyaneshwar (Lalbaug flyover) two-lane, one-way traffic artery was serviceable and used by to 15,000 vehicles/hour, there were daily traffic jams and environmental consequences. Despite the complex and dema
  • Haulotte wraps it up at Turkey’s Osman Gazi Bridge
    July 5, 2016
    French access group Haulotte and the Turkish access distributor and rental group Acarlar continue to contribute to major infrastructure projects in Turkey, including the new Osman Gazi Bridge. The bridge – the third Bosporus crossing - has just been completed with the installation of the last bridge deck. The bridge will reach a height of 252m and the bridge deck will be nearly 26m wide. When it soon opens, the bridge will be the fourth longest suspension bridge in the world by the length of its central