Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Talks continue for 2025 Gordie Howe opening
    January 18, 2023
    The tolled six-lane cable-stayed bridge over the Detroit River will connect the city of Windsor in the Canadian province of Ontario with Detroit in the neighbouring US state of Michigan.
  • Advanced technologies will increase the wear life of bitumen further
    February 28, 2012
    Bitumen has been used for thousands of years, but now a wide variety of products are available that can be added to it to produce blends with improved properties. According to the Refined Bitumen Association (RBA) bitumen is the oldest known engineering material. Indeed, the organisation says that its versatility as a construction material is unparalleled, and having been used as an adhesive, sealant and waterproofing agent for over 8,000 years, its uses include the construction and maintenance of roads, ai
  • Pay attention to The Ray, urges WheelRight’s John Catling
    July 17, 2017
    Development of the connected and sustainable highways is moving quickly in the US and the Far East but progress in Europe is much less impressive. One example of a connected highway that offers an interesting model for European transport planners and policymakers is The Ray, a 29km stretch of Interstate 85 in the state of Georgia. Originally established by a charitable foundation, The Ray offers an inspiring vision of a sustainable highway, even for the near future. Drivers crossing the state line from Ala
  • High-tech, high places: 3M in US and MetService in New Zealand
    August 1, 2017
    The US state of Michigan sets up a high-tech test road while New Zealand’s transport officials buy in some high-tech weather forecasting. The road safety division of 3M will provide the US state of Michigan with lane markings and retroreflective signs for a connected vehicle technologies trial along the I-75 highway. Around 5km of the Interstate 75 work zone in Oakland County will be transformed over the next four months to improve safety for drivers and test advanced vehicle-to-infrastructure technologie