Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Underground routes for highways
    July 20, 2012
    Increasingly, and where possible, roads are being built in tunnels often for environmental reasons, writes Patrick Smith As part of the new M7 motorway development in the southwest of Ireland, the four-lane route crosses the River Shannon near Limerick, before it flows into the Atlantic. Centrepiece of the 10km long Limerick Southern Ring Road is the required tunnelling (675m long), which including the north and south entrance and exit ramps, means it will be 915m long. Completion of the work is planned for
  • Stantec: coming to an infrastructure site near you
    April 13, 2017
    Acquisitive Canadian firm Stantec is snapping up more transportation expertise as it moves out of its home North American market. David Arminas reports. Last December, politicians from the US states of Kentucky and Indiana celebrated the opening of the second of two major bridges. A ribbon-cutting ceremony took place in cold wintry weather on the new 762m-long cable-stayed Lewis and Clark Bridge. The event marked the finish of the prestigious three-and-half-year Ohio River Bridges Project.
  • Flatiron and Dragados win Corpus Christi Bridge deal
    June 25, 2015
    The Texas Transportation Commission has conditionally awarded the two companies, Flatiron and Dragados the contract to design, build and operate a new cable stayed Corpus Christi Harbor Bridge.
  • Major project to construct landmark Bay Bridge in California
    October 31, 2012
    Iconic California crossing will offer seismic safety – Adrian Greeman reports A unique single-span single-tower suspension bridge is the iconic centrepiece of a dramatic renewal of the eastern Bay Bridge in California, crossing from San Francisco to Oakland. Tourists in San Francisco sometimes mix up their bridges, identifying as the famous Golden Gate, the double suspension bridge which runs across the wide San Francisco Bay. These serially linked bridges in fact form the Bay Bridge east to Oakland whereas