Moveable barrier cuts costs, aids motorists

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier. The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the American Council of Engineering Companies of Indiana. Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow Indiana Department of Transportation (INDOT) to take advantage of the favourab
February 20, 2012 Read time: 3 mins
The QuickChange Moveable Barrier from Barrier Systems

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier.

The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the 2853 American Council of Engineering Companies of Indiana.

Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow 2855 Indiana Department of Transportation (INDOT) to take advantage of the favourable bid conditions.

The work, completed late last year, called for replacement of the superstructure for the existing seven-span bridge. A new steel beam superstructure was selected in order to minimise the dead loads and utilise the existing substructure units.

US 31 is a busy urban arterial that carries over 54,000 vehicles per day, and it was apparent that the construction project would significantly impact traffic and cause major delays.

Lick Creek Bridge carries six lanes of traffic, with two through lanes in each direction and a ramp lane in both the northbound and southbound direction.

It was determined that the bridge was too narrow to maintain the current traffic flow during construction, and the original construction plans called for a temporary widening of the bridge that inflated the cost of construction to an estimated US$6 million.

Because US 31 has a directional traffic flow with a significantly higher volume in the northbound lanes during the morning peak and higher southbound volume in the evening peak, the concept of a moveable barrier was introduced.

The QuickChange Moveable Barrier (QMB) from 165 Barrier Systems, would physically separate the northbound and southbound traffic, but it could be quickly reconfigured several times per day to provide two lanes for peak traffic in each direction using a total of only three lanes in a 2/1, 2/2 configuration.

Because the bridge no longer had to be widened, the estimated project cost was revised to $4.8 million, a saving of $1.2 million over the original estimate.

"In addition to the cost savings, the moveable barrier provided benefits to motorists by maintaining the same number of traffic lanes throughout the entire project, and the surrounding neighborhoods benefited from the reduced impact to air quality that is typically created from traffic backups," says Barrier Systems.

"The project exceeded INDOT's original expectations in several categories including overall project cost and potential impact on the motoring public."

Related Content

  • Acrow supplies temporary bridge during Turcot Interchange project
    June 28, 2018
    Acrow Bridge has supplied a long-term temporary modular bridge to main contractor KPH Turcot for its work on the Turcot Interchange reconstruction in Montréal, Canada. The 32.3m-long Turcot modular steel bridge - Acrow’s longest clear span bridge in Canada – is 5m wide and has an orthotropic deck. The rented Acrow components arrived on site late last year and the bridge was opened to traffic in December. It is expected to be in place for two years. The Turcot Interchange is a three-level stack freeway int
  • Bitumen additives raise environmental questions
    February 14, 2012
    New products, including additives, are coming onto the market to help reduce the cost of producing bitumen. Patrick smith reports. According to Eng. Paolo Visconti of Iterchimica, environmental issues and the health and safety of operators of manufacturing plants and workers laying bituminous mixes have raised long debates on the possible harmfulness of fumes which are emitted when heating these mixes at the temperatures (160-180°C) required for their production. "If, on the one hand, the effects on operato
  • Latest VMS keeps world’s motorists moving safely
    April 10, 2013
    VMS for what is thought to be the longest road tunnel in the Middle East, and the installation of the latest VMS technology in Canada’s oldest national park to help motorists travelling through it are among the projects discussed by Guy Woodford. A large volume of VMS from Italian firm Solari has been installed in the new 4.2km-long Zayed Street Tunnel in Abu Dhabi – thought to be the longest in the Middle East. The Solari VMS supply consisted of 204 lane control signs, with Red, Yellow and Green LED pre-de
  • Safety barriers deliver valuable road user protection
    February 14, 2012
    Safety barriers provide an invaluable service for all road users, Mike Woof reports The safety barrier market is a key one for the highway sector, with systems providing valuable protection for all categories of road users. The importance of passive protective devices such as safety barriers can often be overlooked by the road user but is well-understood by highway designers. Redirecting an errant vehicle back into the roadway and preventing it from crossing into traffic flowing in the other direction or fr