India road delivery delays for major projects

India’s road network development programme is facing a series of delays with several major projects now well behind schedule.
June 19, 2017 Read time: 1 min

India’s road network development programme is facing a series of delays with several major projects now well behind schedule. In all 22 road projects stretching some 1,239km and worth a total of US$2.84 billion. The contracts for the 22 projects were awarded from July 2016 to October 2016 but construction work is yet to commence.

For most of the projects, the delays are due to hold-ups in obtaining the necessary environmental permits, securing financing and finalising the acquisition of the land on which the various routes will be built.

Related Content

  • India’s massive demand for bitumen
    March 9, 2016
    India to lead the pack in bitumen consumption - Partha Pratim Basistha reports from the Asian Bitumen Conference. In the emerging global bitumen market, demand is expected to reach 122 million tonnes by 2018. Increasing road construction activities in the fast growing markets of India and China will be the main growth drivers of the bitumen market in Asia. This was the message delivered at the 10th Asian Bitumen Conference held in New Delhi, India from 23rd-24th November 2015. The two-day event, organised b
  • Key route upgrades for Scotland
    July 19, 2012
    Major road projects in Scotland will improve the country’s transport connections. Plans are now in hand to fast-track the project to convert the A9 to dual carriageway status along its entire length. The road is a major transport artery to the north of Scotland, connecting the Central Belt in the south with the northern city of Inverness, providing the main gateway to the north of the country. The plans call for the upgrading of the A9 to dual carriageway status between Perth and Inverness. Work on the 5km
  • Algeria-Mauritania road project
    January 9, 2023
    An Algeria-Mauritania road project is to commence.
  • UAE setting construction agenda
    May 25, 2012
    Talks are now underway again for the US$3 billion Bahrain-Qatar Causeway project, which was delayed largely due to the financial crisis. Work on the 40km causeway project, which is intended to feature both road and rail connections, stopped in June of this year. The project is being handled by a consortium headed by Qatari Diar Real Estate Investment Company (QDREIC) and French firm Vinci Construction. Under the original plan the road links were due to be completed by 2013 and the rail connections by 2015,