India road delivery delays for major projects

India’s road network development programme is facing a series of delays with several major projects now well behind schedule.
June 19, 2017 Read time: 1 min

India’s road network development programme is facing a series of delays with several major projects now well behind schedule. In all 22 road projects stretching some 1,239km and worth a total of US$2.84 billion. The contracts for the 22 projects were awarded from July 2016 to October 2016 but construction work is yet to commence.

For most of the projects, the delays are due to hold-ups in obtaining the necessary environmental permits, securing financing and finalising the acquisition of the land on which the various routes will be built.

Related Content

  • Réunion island road works continue
    September 14, 2022
    The Réunion island road works are continuing.
  • Tendering commencing for Indonesian toll road project
    July 21, 2014
    In Indonesia the tender process is commencing for the new Balikpapan-Samarinda toll road. The project had faced earlier delays due to problems over land acquisition along the route. These have now been solved and the project should be getting underway in October 2014. The Indonesian Government is investing some US$215 million in the project, although the inner of the tender will also be expected to invest in the scheme.
  • New road links will cut congestion in St Petersburg
    June 20, 2016
    Road building will solve the problem of traffic jams in St Petersburg – Eugene Gerden writes The authorities in Russian city St Petersburg plan to solve the problem of traffic jams in the city during the next few years. The strategy is expected to be achieved through road building and the improvement of transport connections between different districts in the city. Implementation of these plans will take place as part of the decree 355 "Of the Strategy of St Petersburg Economic and Social Development
  • Key Colombia tunnel projects delayed
    September 21, 2018
    Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully