India road delivery delays for major projects

India’s road network development programme is facing a series of delays with several major projects now well behind schedule.
June 19, 2017 Read time: 1 min

India’s road network development programme is facing a series of delays with several major projects now well behind schedule. In all 22 road projects stretching some 1,239km and worth a total of US$2.84 billion. The contracts for the 22 projects were awarded from July 2016 to October 2016 but construction work is yet to commence.

For most of the projects, the delays are due to hold-ups in obtaining the necessary environmental permits, securing financing and finalising the acquisition of the land on which the various routes will be built.

Related Content

  • India: Asian Development Bank to support rural road works
    April 28, 2015
    The Asian Development Bank (ADB) said it will provide around US$2 billion for constructing new rural roads in five Indian states, according to The Hindu newspaper. The projects in Assam, Madhya Pradesh, Odisha, Chhattisgarh and West Bengal states, will involve constructing and upgrading 31,000km of rural roads that will improve connectivity to more than 12,500 villages. The move will also provide more employment opportunities in the area, improve school enrolment and provides better remuneration for f
  • Denmark set to appoint preferred bidder for Fehmarnbelt link
    March 14, 2016
    The Danish political parties behind the Fehmarnbelt link have mandated Femern A/S to appoint preferred bidders for the main tunnel work in order to enter into conditional contracts no later than mid-May. Femern A/S is the Danish government-owned company managing the Fehmarn Belt immersed tunnel project between Denmark and Germany. The project was approved by the Danish parliament in April last year. It is supposed to be built, owned - apart from the German land works - and operated by Femern A/S, a su
  • Malaysia’s Pan Borneo Highway project
    October 25, 2019
    Three more contracts are due to be awarded for Malaysia’s important Pan Borneo highway project.
  • Tampere road tunnel - a strategic link for central Finland
    April 4, 2016
    Progress has been good for an important underground road link in Finland reports Adrian Greeman. Assuming all goes well, the new Ranta, or Lakeside, tunnel in Tampere will open in full six months early; traffic could be running by the end of this year. Work on transforming the rundown city centre with new developments will get a major boost. It is a major achievement on a four-year-long project bringing significant benefits to one of Finland's largest cities. From the government's point of view the scheme w