Cost rises again for Columbia’s unfinished La Linea tunnel

Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel. Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November. The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-B
February 3, 2015 Read time: 2 mins
Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel.

Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as 3260 World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November.

The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-Buenaventura corridor. The link, which will be the longest road tunnel in Latin America, will connect Calarca and Cajamarca in the central Corderilla of the Colombian Andes Mountains.

But the tunnel project has met with numerous challenges -- technical, geophysical, financial and legal. Altitude has made work on site difficult, with two tunnel portals at around 2,500m above sea level.

Last December, World Highways reported that the Segundo Centenario consortium, which is building the tunnel, want to push ahead with construction and it would take around $60 million to finish the project.

A new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40% stake in the venture and deliver more capital as required. There are also plans to bring in two strategic partners, the cement firms Cementos Argos and 3016 Cemex. These companies could offer credit lines for the materials such as cement, concrete and steel.

In addition, construction firm Carlos Collins, part of the Segundo Centenario consortium, could transfer funds from the Bogota-Girardot project, in which it also has a stake, into La Linea. The consortium has asked for 13 months to complete work on the tunnel.

Details of the road and tunnel construction were featured in World Highways %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17519 0 oLinkExternal last May Visit &quot;tunnel for colombias calarca cajamarca highway&quot; page false /sections/emergent/features/tunnel-for-colombias-calarca-cajamarca-highway/ false false%>.

For more information on companies in this article

Related Content

  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Brazil: contractors fear more layoffs as DNIT fails to pay up
    November 25, 2014
    The head of Brazil’s association of road constructors has warned of more layoffs unless the National Department of Infrastructure and Transport (DNIT) starts paying its contractors. Jose Alberto Pereira Ribeiro, president of ANEOR – National Association of Road Works - said companies already have been forced to lay off around 1,700 workers in light of non-payment by the government. Another 950 employees are on forced holidays. Ribeiro claimed DNIT failed to meet its financial obligations for September
  • Algeria signs off two contracts of Hauts Plateaux motorway work
    January 5, 2015
    The Algerian Council of Ministers has approved two contracts for stretches of road on the Hauts Plateaux motorway. No details of the contractors were given for the work that is to link Lambidiri to Draa Lahmar via Ouled Fadhel. Construction is expected to take 18 months. Last March, World Highways reported that work on the 1,000km Hauts-Plateaux motorway project was to begin that month. Construction cost for motorway’s 10 sections was estimated to be around US$8.94 billion, according to Algerian Minis
  • Ferrovial loses control of Canada’s 407 Express Toll Road
    August 27, 2019
    Ferrovial has lost control of the 407 International highway in Canada, one of the Spanish group's star assets. The Supreme Court in the province of Ontario has ruled in favour of co-shareholder pension fund Canada Pension Plan Investment Board to buy another stake - 10.01% - in the highway. The shares are up for sale by another shareholder, Montreal-based global infrastructure engineering firm SNC-Lavalin. The court denied Ferrovial, which already has the largest shareholding at 43% in the highway, th