Cost rises again for Columbia’s unfinished La Linea tunnel

Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel. Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November. The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-B
February 3, 2015 Read time: 2 mins
Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel.

Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as 3260 World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November.

The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-Buenaventura corridor. The link, which will be the longest road tunnel in Latin America, will connect Calarca and Cajamarca in the central Corderilla of the Colombian Andes Mountains.

But the tunnel project has met with numerous challenges -- technical, geophysical, financial and legal. Altitude has made work on site difficult, with two tunnel portals at around 2,500m above sea level.

Last December, World Highways reported that the Segundo Centenario consortium, which is building the tunnel, want to push ahead with construction and it would take around $60 million to finish the project.

A new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40% stake in the venture and deliver more capital as required. There are also plans to bring in two strategic partners, the cement firms Cementos Argos and 3016 Cemex. These companies could offer credit lines for the materials such as cement, concrete and steel.

In addition, construction firm Carlos Collins, part of the Segundo Centenario consortium, could transfer funds from the Bogota-Girardot project, in which it also has a stake, into La Linea. The consortium has asked for 13 months to complete work on the tunnel.

Details of the road and tunnel construction were featured in World Highways %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17519 0 oLinkExternal last May Visit &quot;tunnel for colombias calarca cajamarca highway&quot; page false /sections/emergent/features/tunnel-for-colombias-calarca-cajamarca-highway/ false false%>.

For more information on companies in this article

Related Content

  • Solution found for Colombian tunnel project?
    March 12, 2015
    A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Poland: Budimex picks up S3 express road work near Lubin
    December 18, 2014
    The Polish construction consortium of Budimex and Ferrovial Agroman has won a tender to build a 22.6km section of the S3 express road between Silesian town of Legnica in the southwest and Lubin Poludiine, around 170km southeast of the capital Warsaw. The bid by the consortium, in which Budimex has a 95% stake, was nearly US$234 million and construction is expected to take 30 months. Ferrovial Agroman is the engineering and construction arm of Spanish infrastructure group Ferrovial. In early December,
  • North Marmara Motorway connecting roads tenders postponed again
    September 2, 2015
    Tenders for construction of connecting roads for Istanbul's third bridge over the Bosporus have been postponed for the fourth time. A tender for the Kurtkoy-Akyazi motorway tender will be held on March 1 next year with that for the Kinali-Odayeri road will be held a week later, the Dünya Gazetesi newspaper reported. The tenders will be held as part of the 260km North Marmara Motorway project that includes the soon to be completed Yavus Sultan Selim Bridge. Completion of the connecting roads is plan