Moscow to turn from implementation of Fourth Ring Road project

The Moscow City Government plans to complete building of the North-East and North-West Chords, two of the biggest road building projects in the city for the last 15 years The links will be completed during the next several months, according to an official spokesman of the Moscow Government. Both roads are considered as a cheaper alternative to the Fourth Ring Road, the construction of which was considered by the Moscow Government several years ago. However due to huge costs, which are estimated at mo
January 5, 2016 Read time: 4 mins
Moscow suffers heavy traffic at peak periods, with new road projects set to reduce congestion
RSSThe Moscow City Government plans to complete building of the North-East and North-West Chords, two of the biggest road building projects in the city for the last 15 years

The links will be completed during the next several months, according to an official spokesman of the Moscow Government.

Both roads are considered as a cheaper alternative to the Fourth Ring Road, the construction of which was considered by the Moscow Government several years ago. However due to huge costs, which are estimated at more than US$20 billion (RUB 1 trillion) implementation of the Fourth Ring Road project was suspended in 2010.

The North-East Chord should link the Moscow - St Petersburg highway with the Veshnyaki – Lyubertsy road, (which passes through the Moscow region) and will be the continuation of the Moscow - St Petersburg road.

The Chord will connect major highways in the north-east of Moscow, including the Dmitrov, Altufevskoe, Yaroslavl and Schelkovskoe routes.

Under the terms of the project, the length of the future toll-free road will be about 25km. According to state plans, the new road should reduce the traffic load on the Moscow Ring Road, the Third Ring Road, outbound routes, as well as downtown of Moscow.

Building of the North-East Chord has been carried out since 2008. The volume of investments is estimated at $5.5 billion (RUB 135 billion), of which $2.85 billion (RUB 70 billion) has already been allocated from the federal budget and the budget of the Moscow City Government.

Oleg Skvortsov, President of RHODES, the Association of research organisations in the field of road building, supports the idea of the establishment of such chord road systems in Moscow.

According to Skvortsov, ring roads, which were built in the city under Yury Luzhkov, the previous Moscow mayor, do not solve the problem of traffic jams in the city.

Skvortsov explained, "Chords, unlike ring roads, pass outside the city. In addition, in the case of building of several chords, they may form the ring. Another advantage is that building a straight road is always cheaper, compared to curved roads.”

According to initial plans of the Moscow City Government, building of the chord should be completed in the first half of 2016, however, due to the current crisis in Russia, caused by Western sanctions, implementation of the project may be suspended until 2017, mainly due to a shortage of funds in the Russian federal budget and the budget of Moscow city.  

Due to this, the Moscow City Government has already begun a search for private investors, who may participate in the project.

There is a possibility that building of the road may be finished by the Leader Group of Companies, Russia’s largest company in the market of trust management, with a total value of operating assets estimated at $17.76 billion (RUB 436 billion). The project is expected to be implemented on the basis of concession.

At the same time, in addition to North-East Chord, as part of the plans, the Moscow City Government is building the North-West Chord, which will link the north-eastern and south-western parts of the city.

The idea for building the chord was first put forward in 1971, however implementation of the project only began in 2011. Building of the road should be completed by 2017. It will be approximately 29km long and will stretch from Skolkovo to the Yaroslavl highway.

According to initial plans of the Moscow City Government, the volume of investments in the building of the North-West Chord should reach $1.3 billion (RUB 32 billion), however, to date, these figures have already risen to $2.5 billion (RUB 63 billion).

Successful implementation of both projects will allow the Moscow City Government to finally cancel the building of the Fourth Ring Road, the road building project, which, according to preliminary calculations of the Moscow authorities, would become one of the most expensive in the history of Russian and Moscow road building.

According to an official spokesman of Sergey Sobyanin, the mayor of Moscow, the cost of building the road is comparable to the Central Artery/Tunnel Project, a megaproject in Boston that rerouted the Central Artery (Interstate 93)––the chief highway through the heart of the city—into the 5.6km Thomas P O'Neill Jr Tunnel, the volume of investments in which implementation amounted to US$14.6 billion.

Sergey Sobyanin said, "Due to such enormous costs, we are not ready to build the Fourth Ring Road. That makes no sense. We have already built the Third Ring Road, however this has not resulted in a significant improvement of the situation with road traffic in the city. The cost of building the Fourth Ring Road is more than 1 trillion rubles, which means that the city would have to suspend implementation of other road building projects for about ten years.”
RSS

Related Content

  • Russian taxation on the rise
    December 3, 2012
    In Russia the Ministry of Transport proposal to introduce payment for the owners of heavyweight trucks over 12tonnes could increase cargo transportation tariffs by 10%. Consumer goods prices are also expected to rise, especially outside Moscow and St Petersburg. Leonid Shlyapnikov, CEO of Sovtransavtoekspeditsiya, thinks shipping companies may incur additional expenses on the installation of on-board computers, GLONASS navigators and placement on unified register. New norms and fees are to be added to the e
  • Brazil: Phase 2 of PAC infrastructure programme shows results
    December 18, 2014
    Brazil has built nearly 5,200km of roads in the past four years, according to a review of the federal government's PAC Phase 2 accelerated economic growth programme. Around 1,400 of the 5,200km were built under long-term concessions and another 7,000km are under construction. Total investment has been around US$24.43 billion. PAC is a strategic investment programme that combines management initiatives and public works, according to the World Bank. The first phase, launched in 2007, saw around $349 bil
  • Tunnel breakthrough for new Auckland link in New Zealand
    October 8, 2014
    Auckland’s Western Ring Route project update - Mary Bell writes. A number of integrated projects in Auckland, New Zealand, will improve the lot of road users and cyclists, and significantly alter the topography of the city’s motorway. On September 29th the tunnel boring machine digging the first of twin road tunnels beneath the city broke into daylight after 10 months underground. The new 2.4km-long Waterview tunnels will connect the city’s Northwestern and Southwestern motorways, each carrying three lane
  • Moscow’s first toll road is being planned
    May 21, 2013
    In Russia’s capital Moscow the finishing touches are being put to a plan to construct the city’s first tolled link. The northern relief road for Kutuzovsky prospect is expected to cost US$1.91 billion to build and will stretch a distance of 10.3km. The tender process for the concession package is being prepared at present and is expected to open for bids shortly. Once complete the new link will connect Moscow’s business centre with Molodogvardeyskaya junction. Meanwhile in the Russian city of Tula, some 193