RMD Kwikform 3D viaduct design aids single concrete pour in Norway

Engineers with RMD Kwikform used 3D modelling to overcome challenging terrain and tight schedules for pouring a single-deck concrete viaduct in mid-Norway. The Doro Viaduct is a post-tension three-span single-carriageway measuring 9.5m wide. It forms an important part of the large realignment of the E39 Harangen-Høgkjølen route in the Trondheim mid-region of Norway. The project needed a formwork and shoring solution to support a 93m-long, 750m3 single-deck pour for the three span Doro viaduct in Norway. For
March 13, 2015 Read time: 4 mins
Five R700 trusses were craned into position
Engineers with RMD Kwikform used 3D modelling to overcome challenging terrain and tight schedules for pouring a single-deck concrete viaduct in mid-Norway.

The Doro Viaduct is a post-tension three-span single-carriageway measuring 9.5m wide. It forms an important part of the large realignment of the E39 Harangen-Høgkjølen route in the Trondheim mid-region of Norway.

The project needed a formwork and shoring solution to support a 93m-long, 750m3 single-deck pour for the three span Doro viaduct in Norway.

Formwork and shoring for the project was supplied to specialist concrete contractor Sobstad by local formwork equipment supplier Hansmark, which has completed several other smaller projects for Kwikform.

The Kwikform engineering team was able to combine existing stocks of Rapidshor shoring and Superslim soldiers with their heavy duty Megashor shoring and R700 trusses for a complete viaduct solution.

But the pressure was on Sobstad to complete the single pour during August. Before this, Kwikform also had to work fast and ensure the right amount of equipment was shipped to the site for the start of erection work in March.

To assure the project went smoothly and efficiently, a 3D CAD model of the viaduct was created using information received from the site. This enabled production of detailed design drawings that in turn allowed accurate erection of the equipment and automatic equipment take-offs.

Three spans, measuring 29m, 35m and 29m requiring shoring support above the river running below in the Doro valley. Fortunately, the narrow width of the river meant only a clear span falsework solution was needed for one of the three viaduct spans.

To support this first 29m span, Kwikform designed a clear-span solution using five pairs of 25m-long R700 trusses, each weighing 11tonnes. One end of the trusses was supported by a six-legged Megashor tower mounted on the pier base with the other end sitting on a foundation near the abutment. Loadings from the trusses were transferred to the Megashor tower by an 11.5m-long header beam supporter by three 3m distribution beams.

The five R700 trusses were then craned into position and then steel Superslim soldiers were mounted on top of the trusses. A partial access platform was installed on top of the trusses to allow for the installation of a Rapidshor steel shoring birdcage arrangement, around 3.5m tall. By combining Rapidshor U heads at the base and top of the legs with bracing supports, the birdcage-style shoring structure was able to support another layer of Superslim soldier beams and timber secondary beams for the bridge deck soffit.

Because of the additional second and third spans supported by Rapidshor birdcage arrangements from the ground, varying in height from 8-14m, the viaduct with its 4.2% deck incline could be cast in one continuous pour.

“The whole site was very exposed and so the solution needed to support not only the loadings pressures from the single concrete pour, but to be robust enough to cope with high winds,” said Odd Inge Fremo, manager of the Trondheim area office of Hansmark.

“With the truss arrangement we wanted to minimise the amount of equipment needed onsite, yet be able to preassemble units next to the structure. With the Megashor tower we could lift sections into place, sequencing the build and similarly, because the R700 trusses were kept under the capacity of our site crane, we were able to simply manoeuvre them into place with minimal effort.”

He said that by using guide plates on the main header beam, when it came to extraction, the site team were able to simply move the trusses to one side, swinging them out safely using the crane. This saved both time and money.

Apart from supplying the equipment for the single deck pour, 319 RMD Kwikform also engineered Rapidshor access towers used to construct bridge piers that would eventually support the viaduct.

RMD Kwikform had, prior to the Doro project, supplied Hansmark with Rapidshor solutions for the construction of the smaller Hallstein and Graven bridges on the same highway improvement programme.

For more information on companies in this article

Related Content

  • Norway moves toward more E39 coastal road improvements
    April 4, 2019
    Norway is working on plans to make more of the major north-south E39 coastal route a ferry-free highway, coasting €35.3 billion, according to media. In Norway, the trans-European route 39 is part national road system and is developed and maintained by the public roads administration. It runs for 1,330km along the coast from Klett just south of Trondheim to Nørresundby. Norway’s E39 is mostly a two-lane undivided road with only relatively short sections near Stavanger, Trondheim and Bergen being motorw
  • HDR’s twin Rockingham bridges win PCI award
    February 12, 2021
    The award from the Precast Concrete Institute is a third win for HDR projects.
  • Tubeshor shoring system
    December 10, 2024

    Altrad RMD Kwikform has launched a solution to reduce the effects of thermal loading - the Tubeshor Active Thermal Compensator, ATC.

    The Tubeshor hybrid hydraulic shoring system is used for propping waler beams or capping beams of large excavations. Altrad RMD Kwikform, an above and below ground temporary works specialist, said it comes in a range of diameters to cater for all duties of shoring requirement.

  • Norway mega-project contract for Fugro
    December 20, 2017
    The largest road project in Norway’s history has seen Fugro win a second major contract from the Norwegian Public Roads Administration (NPRA). The work on the E39 Coastal Highway is for the construction of a 1,100km route from Kristiansand in the south to Trondheim in central Norway. This project is expected cost around €34.4 billion (NOK 340 billion).