Skip to main content

Key Botswana road network gets an upgrade

Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way. A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe b
June 30, 2014 Read time: 4 mins
The RM300 recycler is carrying out valuable work on a key road in Botswana
Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade

This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way.

A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe border some 90km distant. From there commercial traffic continues on to destinations that include Zambia and the DRC.

The contract for the reconstruction of the Tonota to Francistown route, covering a distance of approximately 30km, was awarded to China Railway Seventh Group Botswana (CRSG Botswana) in August 2012 by Botswana’s Ministry of Transport and Communications, Roads Department. The 30-month construction programme commenced in May 2013 following an initial six-month mobilisation period entailing the relocation of water, sewage, telecommunication and electrical services. The consulting engineers are Pula Consultants, based in Botswana.

In addition to the installation of three major in-situ box culverts to cater for the extended pavement width, a number of simply supported independent bridges are being constructed alongside the existing Tholodi, Shashe and Bodumatau. The Tati River Bridge on the outskirts of Francistown is the exception. Here the structure is being widened equally on each side from the existing width of 10.63m to the new deck width of 28.55m, maintaining the current road centreline.

Tholodi’s new carriageway bridge will be a 36.15m-long 3 x 12m Span structure. Shashe will feature a new 144.6m-long 12 x 12m Span bridge, and Bodumatau a new 24.1m-long structure with 2 x 12m spans.

All three bridges will have an overall deck width of 11m with a road width between parapets of 10.4m on a 2,5% crossfall. Bridge deck Cross-sections consist of precast, ordinarily reinforced inverted T-Type beams with in-situ concrete between and on top, providing an overall deck thickness of 710mm. Tati River Bridge, measuring 108.45m in length, will also employ precast beams for the deck widening.

General rehabilitation and maintenance of the existing bridges is also being undertaken, along with the construction of concrete New Jersey type parapets that will replace existing steel handrails. New and existing bridges will be surfaced with a 50mm thick asphalt overlay.

Running in parallel with the bridge programme, road works along the Tonata to Francistown section are extensive. In addition to new roadbed preparation, construction of in-situ reworked and new cement stabilised lower and upper sub-base layers form a major portion of the contract.

CRSG’s scope of works also includes the widening of existing cuts and fills, benching into old fills or the construction of new cuts and fills; Plus horizontal and/or vertical realignment of the existing road in order to improve design speed, which is generally 120km/h along rural sections, and 80 – 60 km/h through built-up areas.

The existing Thapama Traffic Circle within Francistown will also be remodelled as a grade separated intersection, together with the construction of two access roads.

New construction, as well as reconstruction of the existing pavement is being carried out by a 178 Caterpillar RM300, which forms the critical path of the road contracts programme. Sold and supported by local dealer Barloworld Equipment, the RM300 is working alongside CRSG Botswana’s predominately CAT earthmoving fleet, comprising graders, excavators and rollers.

In addition to its RM300 deployed on the A1, CRSG Botswana also has a CAT RM500 deployed in Zambia, where the company is currently working on a range of construction projects. According to CRSG, both machines are providing good production results with high availability.

Wholly owned by China Railway Group Limited, CRSG has established a strong presence on the African continent, with subsidiaries formed in Botswana, Zambia, Mozambique, Tanzania, Uganda, Ethiopia, Senegal, and Sierra Leone.

The Tonota to Francistown project is the second Botswana contract awarded to CRSG. The first, valued at around $21.8 million, was completed in 2011, entailing the upgrading of a 38km gravel section between Ngoma and Kachikau to a bitumen double-seal single-lane riding surface, which was officially opened in December of that year.

For more information on companies in this article

Related Content

  • Recycling machines have helped add new lanes to an Italian highway
    May 30, 2013
    The use of recycling and stabilisation equipment has played a key role in adding new lanes to a congested Italian highway. Running from Bologna to Taranto, the A14 Autostrade has seen a major increase in traffic volumes for several years. Data shows that traffic has increased around 4% year on year with some 110,000 vehicles using the highway/day. The traffic growth trend looks set to continue and this resulted in the Italian Government opting to upgrade and widen the route.
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Shay Murtagh Precast bridges gap at Whitley Junction in Coventry
    May 22, 2018
    Shay Murtagh Precast has been supplying main contractor Costain with all precast units for the Whitley Junction Improvement works in Coventry, England. Costain was contracted by Coventry City Council to remodel the junction on the A444, one of the busiest routes in the city. Shay Murtagh Precast manufactured and delivered 30 Y5 beams, 4 YE5 beams, 2 cast on parapets as well as 750 Hexlok Panels with feature finish for the reinforced soil walls and abutments. Shay Murtagh Precast manufactured 22 bridge be