New bypass for Meghalaya, India

A new two-lane road has been built in Meghalaya, India, providing a challenging project for the construction team The new road lies at a comparatively high altitude and provides a bypass around Shillong, the capital of Meghalaya and which is one of the smallest states in India. Shillong is located 1,496m above sea level, with the highest point being Shillong Peak at almost 2,000m, and the area has a much cooler climate than the rest of tropical India. Shillong is also only 55km away from Mawsynram, which is
November 21, 2014 Read time: 3 mins
Volvo CE machines worked successfully on the Shillong bypass project in India

A new two-lane road has been built in Meghalaya, India, providing a challenging project for the construction team

The new road lies at a comparatively high altitude and provides a bypass around Shillong, the capital of Meghalaya and which is one of the smallest states in India.

Shillong is located 1,496m above sea level, with the highest point being Shillong Peak at almost 2,000m, and the area has a much cooler climate than the rest of tropical India. Shillong is also only 55km away from Mawsynram, which is officially the world’s wettest place.

The Shillong bypass connects the top of the main NH-40 highway starting at Umiam in Ri-Bhoi district to the bottom of the NH-44 highway at Mawryngknend in the East Khasi Hills district. It included building about 500km of road for two-lane traffic as well as a 2.5m shoulder on each side. The 3577 National Highway Authority of India (NHAI) awarded the project to Shillong Expressway, which then contracted out the work to infrastructure company, InfraProjects.

The total project cost an estimated US$39.8 million (2,510 million Rupees) and was completed in spring 2014, two years after the project commenced. The work was finished before its scheduled completion date and has raised the expectation of more road construction in the region. Two major high level steel girder bridges were also constructed, 45m long by 30m high, as well as five minor bridges, an underpass, four bypasses, two major junctions, 64 small junctions and seven bus bays.

GR Infra Projects used excavators from 359 Volvo CE throughout the project, including five 14tonne class EC140BLCs and two 20tonne EC210B-Series models to dig and remove overburden. These were supplied and supported by local Volvo CE dealer, Esdee Solutech.

Because of the mountainous terrain, a lot of cut and fill was required, resulting in a huge amount of earthmoving in order to keep to schedule. For day-to-day operations the company also used other Volvo CE machines including, four DD100 asphalt compactors, two SD110 soil compactors, G930 graders, L120 wheeled loaders and an ABG7820
asphalt paver.

GR Infra Projects specialises in building highways and bridges across India, employing about 130 civil engineers. The company has successfully delivered over 150 road projects, including 3,200km in Rajasthan, Haryana, UP, Bihar, Jharkhand and the North-East, almost always being finished ahead of the completion date. GR Infra Projects commented that it is a first for the north-east region in that a highway of this magnitude has been completed ahead of schedule.

For more information on companies in this article

Related Content

  • Linking Kenya and Uganda with a new road project
    May 10, 2018
    An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to a
  • Volvo machines facilitate German highway construction project
    August 15, 2014
    German contractor Gebrüder Bantle is working on a large ring road project in Bösingen, excavating and building 6km of highway and nine bridges. The region’s main road, the B462, provides an important link between the A5 Rheintalautobahn and A81 Stuttgart highways. The B462 carries some 12,000 vehicles/day and suffers congestion at peak periods, so a new ring road will help reduce delays for commuters. The Dunningen project consists of a 6.4km ring road, nine bridges and several access roads. Gebrüder Bantle
  • India investing in road infrastructure
    January 16, 2015
    The Indian Government has announced plans to build 7,300km of roads and 48 bridges. The programme is being handled by India's Ministry of Road Transport and Highways and is called the Road Requirement Plan (RRP) Phase-2. The new roads will be constructed in the so-called ‘red zone’. The project is expected to cost some US$1.72 billion, and it will include the construction of roads, highways and 48 bridges. The ‘red zone’ areas have been affected by left wing extremism, namely the Naxalites. As of January 20
  • Volvo CE is further developing its presence in road construction
    October 3, 2014
    The road business has benefited from fairly constant levels of trading in recent years and even during the downturn, construction operations only fell by a comparatively small quantity during the downturn. Darren Fitch, director for road machinery for the EMEA region within Volvo CE said, “The road construction sector has been far less cyclical than other construction markets.” The global market for road machinery is healthy at present and he said, “We’re having a good year.”