Bechtel achieves tricky bridge replacement in tight timeframe

Contractor Bechtel has worked with Network Rail to complete a major road bridge upgrade in the UK. A construction team worked 104 hours consecutively to replace the bridge, located at Reading Station.
March 21, 2012 Read time: 3 mins
Contractor 4138 Bechtel has worked with 4139 Network Rail to complete a major road bridge upgrade in the UK. A construction team worked 104 hours consecutively to replace the bridge, located at Reading Station.

The work forms part of the Reading Station Area Redevelopment project in England and involved installing a new bridge at Cow Lane.

The project was carried out within a tight time frame of 104 hours while the Reading West Curve rail line was taken out of commission for the work. The task of replacing Cow Lane Bridge started at 5pm on December 24th, when the rail freight line above was closed so that demolition of the old 6m span bridge could take place.

In the evening of December 26th, a self-propelled modular transporter lifted the new 14m span, reinforced concrete bridge into place. This led to the on time hand back to operations of the Reading Western Curve.

The bridge move was similar to the Caversham Bridge deck lift delivered by Bechtel, Network Rail, and contractors in 2010. However, in this case, the task was even more complex as instead of the new bridge being moved on site in pieces, here the deck, abutment, wing walls and anchor blocks were lifted as a single, complete 1,600tonne unit. More than 270 people worked around the clock to complete the work on time and to ensure that on 27th December, trains could run as scheduled. “As we were moving a whole bridge into place there was no margin for error. This was a complex task and the results are testimony to what can be achieved through collaboration in the rail industry and with its partners,” said Wayne Chin, implementation director, Bechtel. The bridge replacement is part of Network Rail’s £850 million improvement programme for Reading station and the surrounding area.

Cow Lane Bridge was a notorious bottleneck in the Reading area but the new bridge can accommodate two lanes of traffic including double decker buses, a cycle path and pavement which will help to reduce congestion. "The Cow Lane works went very well indeed. The team overcame some significant problems. When the old Cow Lane bridge was removed, the ground was found to be much more waterlogged than had been expected, and we had to spend around seven hours in extra preparation before we could start to move the new bridge. Despite this, we caught up the time and handed back the possession with four minutes to spare, which is a testament to the resourcefulness and determination of the team”, said Robbie Burns, delivery director for Wales and West, Network Rail.

Additionally, during this time the Reading Station Area Redevelopment project successfully delivered substantial station works including commissioning of the southern lines new platform 4 complete with new track and signalling system, widening of existing Platform 10 and the station platform renumbering.

For more information on companies in this article

Related Content

  • Italy’s resurgence
    June 22, 2020
    Despite the COVID-19 lockdown in Italy – one of the world’s hardest hit nations –the Genoa Bridge replacement continues, with more deck sections in position
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli
  • Pre-stressed bridge decks use modular formwork system
    July 9, 2012
    Imaginative formwork, often using modular components, is helping to shape some challenging bridges worldwide. Patrick Smith reports Traffic volumes in and around Prague have swollen massively in recent years, pushing the existing road network to the limits of its capacity. To permanently ease congestion in the Czech capital's centre, a multi-lane orbital motorway is under construction as a high capacity bypass for central Prague and to link up all the motorways and other major highways radiating from the ci
  • Highly relevant: Denmark’s asset management for bridges
    July 12, 2019
    A well-maintained road bridge network is vital to Denmark’s economy. David Arminas caught up with Niels Pedersen, head of bridges at the Danish Road Directorate Denmark, being a country mainly of islands, relies on its bridges and tunnels to help unify the nation culturally. It also means that they are vastly more important to the economic well-being of the nation than in most other states. The World Bank has classified Denmark as a high-income economy. In 2017 it ranked 16th globally in terms of gros