Volvo trucks on the move at Lummen

Construction company Jan De Nul is using a fleet of Volvo machines for a key highway project in Belgium. The machines have been able to move 26,000m³/weekend on the project to upgrade a highway junction at Lummen, a small town 60km from Belgian capital Brussels. A fleet of 16 Volvo ADTs is being used for the work, to improve the intersection between the E313 and E314, which had become an accident blackspot. Designed some 50 years ago, the roads provide important links from Leuven, Antwerp and the port of Os
February 29, 2012 Read time: 2 mins
Time constraints meant the productive Volvo machines fitted the bill for a Belgian highway project
Construction company 3150 Jan de Nul is using a fleet of 2394 Volvo machines for a key highway project in Belgium. The machines have been able to move 26,000m³/weekend on the project to upgrade a highway junction at Lummen, a small town 60km from Belgian capital Brussels.

A fleet of 16 Volvo ADTs is being used for the work, to improve the intersection between the E313 and E314, which had become an accident blackspot. Designed some 50 years ago, the roads provide important links from Leuven, Antwerp and the port of Ostend in the west, to the Netherlands in the north and Germany in the east.

One of the biggest challenges of the €10 million project has been cutting through the embankment supporting the E313 in two places, removing 14,000m³ of soil from the first point and 12,000m³ from the second, and building two concrete bridges.

The bridges, built on site, weigh 6,000tonnes each and stand 40m wide, 40m deep and almost 10m high. These have to be shunted into place using specialist hydraulic jacks before pavers relay the surfaces across the top. The contractor has had to ensure the entire first phase of the project could be completed within a single weekend so that the E313 could be re-opened in time for the Monday morning rush-hour.

For more information on companies in this article

Related Content

  • Advanced method for South Africa bridge construction
    May 16, 2016
    A sophisticated construction method has been used for the first time in South Africa for a suspended bridge project This novel method of bridge construction was used on a major road upgrade project for the South African National Roads Agency Limited (SANRAL). Main contractor Lonerock Construction, and subcontractor Tzandeboo Construction, used RMD Kwikform’s Megatruss system to construct a 60m-long bridge while suspended mid-air over the live N4 highway. Lonerock Construction’s US$8.5 million (R132
  • India rushing to improve its highway system
    February 9, 2012
    Despite the world economic slowdown, India still seems in a rush to improve its highway system as Patrick Smith reports. Later this year India will be seen by hundreds of millions worldwide when the country's capital New Delhi hosts its biggest event ever.
  • Building a replacement bridge in record time
    March 13, 2023
    The construction of a new bridge in Pittsburgh, Pennsylvania to replace a collapsed structure has been carried out in record time
  • Giving four hours back to the day… and much more
    October 7, 2019
    A 20km long elevated expressway in Dhaka will be one of Bangladesh’s first Public Private Partnership transport projects – words and pictures by Ruby Kitching, on behalf of Mott MacDonald.