UV lining is highway drainage first for UK motorway upgrade

Drainage specialist Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK. Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire. Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being
December 19, 2017 Read time: 3 mins

Drainage specialist 7891 Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK

Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire.

Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being replaced, during a motorway upgrade project in the UK. Liners are designed to give the pipes additional structural strength to meet the 50-year asset lifespan specified by Highways England.

UV cure in-place pipe lining (CIPP) is ideally suited to working in highway environments, said Lanes. Compared with the only other viable system, hot water CIPP lining, it is faster, needs less equipment and fewer personnel. It can also be carried out in a more confined space and generates no toxic water waste.

The Smart Motorway upgrade is tackling congestion and improving journey times by converting the hard shoulder to a permanent extra lane. As well, variable speed limits are added to keep traffic steadily moving to help prevent tailbacks caused by sudden braking.

In the first phase of the programme, Lanes is lining pipes with diameters of up to 600mm along 13km of the northbound M6 carriageway.

Carillion Kier section manager Chris Padden said UV lining is only just now available in the UK.  "The other option is to install new drainage lines in deep trenches, which has additional health and safety risks, takes longer and can be more costly than UV lining.”

Padden said that Lanes has achieved the target of lining around 600m of pipework a week. Simon Bull, manager of Lanes Group's lining division, said it was a challenge. "To do it while working in a 3.5m-wide space with 135,000 vehicles passing each day just inches away, while working around the needs of other construction colleagues, has been a very interesting challenge indeed."

Lanes has deployed two full-time UV lining teams on the project, along with supporting CCTV survey and jet-vac tanker teams. To speed up the lining process, UV liners up to 200m long are being installed.

"We've had to overcome major challenges, including the need to find buried manholes, refurbish other ones, open up new liner entry and exit points and empty very large amounts of silt and debris from pipes before liners can be installed,” said Bull.

"The learning curve has been steep and intense, but we have rapidly developed new techniques and procedures that will allow us to replicate this sort of success with future large highway schemes."

For more information on companies in this article

Related Content

  • Uretek delivers voided soils treatment for UK’s M3 Smart Motorway
    February 8, 2018
    Ground engineering specialist Uretek has been treating voided soils as part of maintenance following completion of the UK’s M3 Smart Motorway project. Work is between junctions 2 and 4a where Uretek has provided a non-disruptive alternative to conventional underpinning to solve foundation subsidence problems. The focus for Uretek is an old 900mm corrugated pipe, 73m long. The old pipe has had a new 700mm pipe inserted inside. However, the old pipe is rusting and rapidly deteriorating.
  • Faster and more efficient earthmoving with machine control
    December 19, 2017
    The use of sophisticated machine control tools from Trimble has helped US contractor Beaver Excavating deliver a project more efficiently. In the US, earthworks contractor Beaver Excavating is testing Trimble’s new machine control platform and is achieving high accuracy and consistent excavation and grading in less time. Jim Sterling, survey and GPS manager for Beaver Excavating, explained that the company has been a longtime Trimble customer. Over the years, the company has added additional machine
  • Highways England tests ghostbusters
    March 9, 2021
    Highways England is testing seven new road marking products as part of a major international project to rid road surfaces of confusing ghost markings
  • Managing urban motorway complexity in Sydney
    October 4, 2012
    Sydney’s Hills M2 motorway is being widened while still carrying traffic and meeting tough environmental criteria More than 100,000 vehicles and over 27,000 bus commuters use the Hills M2 motorway on a typical workday, making it one of Sydney’s busiest motorway corridors. Owned and managed by Hills Motorway Ltd (HML) and a key part of the city’s orbital motorway network, the road stretches over 21km, providing a seamless link between the Lane Cove Tunnel and Westlink M7. The Hills M2 Upgrade is one of many