UV lining is highway drainage first for UK motorway upgrade

Drainage specialist Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK. Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire. Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being
December 19, 2017 Read time: 3 mins

Drainage specialist 7891 Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK

Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire.

Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being replaced, during a motorway upgrade project in the UK. Liners are designed to give the pipes additional structural strength to meet the 50-year asset lifespan specified by Highways England.

UV cure in-place pipe lining (CIPP) is ideally suited to working in highway environments, said Lanes. Compared with the only other viable system, hot water CIPP lining, it is faster, needs less equipment and fewer personnel. It can also be carried out in a more confined space and generates no toxic water waste.

The Smart Motorway upgrade is tackling congestion and improving journey times by converting the hard shoulder to a permanent extra lane. As well, variable speed limits are added to keep traffic steadily moving to help prevent tailbacks caused by sudden braking.

In the first phase of the programme, Lanes is lining pipes with diameters of up to 600mm along 13km of the northbound M6 carriageway.

Carillion Kier section manager Chris Padden said UV lining is only just now available in the UK.  "The other option is to install new drainage lines in deep trenches, which has additional health and safety risks, takes longer and can be more costly than UV lining.”

Padden said that Lanes has achieved the target of lining around 600m of pipework a week. Simon Bull, manager of Lanes Group's lining division, said it was a challenge. "To do it while working in a 3.5m-wide space with 135,000 vehicles passing each day just inches away, while working around the needs of other construction colleagues, has been a very interesting challenge indeed."

Lanes has deployed two full-time UV lining teams on the project, along with supporting CCTV survey and jet-vac tanker teams. To speed up the lining process, UV liners up to 200m long are being installed.

"We've had to overcome major challenges, including the need to find buried manholes, refurbish other ones, open up new liner entry and exit points and empty very large amounts of silt and debris from pipes before liners can be installed,” said Bull.

"The learning curve has been steep and intense, but we have rapidly developed new techniques and procedures that will allow us to replicate this sort of success with future large highway schemes."

For more information on companies in this article

Related Content

  • Work begins on Stockholm’s new bypass
    August 22, 2016
    The first tunnels are being excavated for the huge bypass tunnel in Sweden’s capital Stockholm – Adrian Greeman writes. After years of preparation and design, blasting and rock moving for Sweden's largest infrastructure project began south of the city this year. It sets in train a decade-long project that will create a new half-ring dual three-lane motorway for the city, 20km long. With most of it deep underground, it will also be one of Europe's largest ever road tunnels. The scheme is aimed at transformin
  • THIS is a Paving Project– The I-15 CORE
    December 20, 2012
    Provo, Utah – The scope of the I-15 Corridor Expansion Project (I-15 CORE) in the state of Utah is nearly unprecedented because of the size of the project and the short completion deadline. Twenty-four miles (38.6 km) of removal and replacement of Interstate 15 between Lehi and Spanish Fork, widening the number of traveling lanes by two, for up to six lanes in each direction in 35 months. The new 364 lane miles (586 km) of concrete roadway will be slipformed 12 or 12.5 inches (305 or 318 mm) thick for a tot
  • White lines out!
    February 24, 2012
    Productive highway line marking removal is possible with the new Starjet-Plus model from NLB. Featuring a novel water jet system, this machine helps contractors remove more pavement marking or runway rubber/shift than before. This is said to be the first high-pressure water jet system featuring on-board filtration, allowing users to fill the water tank once and work all day without stopping to refill.
  • Fluor wins award from Highways England
    November 5, 2015
    Fluor Corporation has won an achievement award from Highways England for its National Roads Telecommunications Services (NRTS) project. This has been recognised by Highways England for achieving 3 million safe working hours while executing the project across England’s operational motorways and trunk roads. The Significant Achievement Award for Safety was presented by David Brewer, Highways England’s network delivery and development executive director to Kevin Hamer, Highways England NRTS contract manage