Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
February 17, 2012 Read time: 4 mins
Harsco Infrastructure is playing a vital role providing specialist systems for the A80 upgrade in Scotland
Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard.

The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between; 2.7km of the existing A80 road upgraded to three-lane motorway; and almost 7.3km of the existing A80 upgraded to dual-lane motorway with hard shoulders and climbing lanes.

Work on the project has required extensive demolition and reconstruction on existing structures along the route, including the widening of existing bridges and construction of new ones. This is complicated because as a vital arterial route across Scotland's most densely populated region, the road must remain in use throughout the construction period.

1483 Harsco Infrastructure is playing a vital role providing specialist access, formwork and falsework systems.

Concrete and civil engineering specialist 2805 T Mac Construction is carrying out all the on-line work, constructing new bridges and extensions to existing bridges on the main route, some 16 structures.

T-Mac was awarded the subcontract via a traditional competitive tender process and part of its winning bid was a methodology developed in partnership with Harsco Infrastructure, to minimise disruption on the A80 by closing off the hard shoulder and slow lane.

The work requires a varied approach to access and formwork. This not only entails considerable health and safety risk, but also imposes significant logistical and design problems. The safety challenges have been met by using Harsco Infrastructure's equipment to create an enclosed working area to isolate the workforce from the traffic, which presents challenges as space within the route is limited.

"We are utilising a variety of systems from our portfolio to offer workable and time saving solutions" says David Hancock, sales manager for Harsco Infrastructure.

CUPLOK and MkII Soldier Falsework components are used to create a safe hydrodemolition deck under each bridge which serves as a working platform, as well as access for steel-fixing operatives before the introduction of falsework for the new in situ concrete.

"Essentially, the work involves hydrodemolition to break out existing concrete to expose the steel reinforcement before erecting formwork, stitching in the new rebar and casting the bridge extensions," explains T-Mac managing director Mike Traynor.

The newly-widened carriageways, the existing bridge cantilevers and RC bridge beams are partially demolished and new ones cast. The bridge cantilevers are then extended at either side of the decks and new parapets formed. The central sections of the carriageway are also being strengthened by casting new in situ concrete beams and in situ soffits.

"We planned this project for months in conjunction with the main contractor and sub-contractor to ensure the correct solutions for each individual structure. This included the use of our MULTIFORM parapet brackets, for on-line as well as off-line bridge structures," said Hancock.

T-Mac also used the TOPEC soffit panel system supported by modular aluminium GASS legs for the soffit stages on the existing structures reinstatement, due to extremely restricted work space on these structures.

"TOPEC allows the contractor to fit large soffit areas of completed falsework by simply lifting the aluminium panels into place because they are lightweight. Traditional falsework solutions would have required prolonged work in a confined space for both erecting and striking the system," said Hancock.

The original plan was to complete all the extension work on the southern (westbound) carriageway, then switch to the northern (eastbound) side and then travel back to Haggs, carrying out bridge strengthening work along the central reserve. However, the need to adapt to unforeseen circumstances has resulted in a flexible working regime and the methodology has altered slightly.

"This project has demanded the highest possible level of planning, engineering, design and logistics. In January 2010 we had the worst winter weather for several years, with record low temperatures and heavy snow but although the project suffered delays, the contractors have managed to adapt to the conditions and the final completion date has not been affected. The meticulous planning has paid off," Hancock added.

For more information on companies in this article

Related Content

  • Tunisia is benefiting from key highway expansion
    November 28, 2012
    Work is underway in Tunisia on the westbound Highway from capital Tunis towards the Algerian border. This 60km link will run from the town of Oued Zarga to Boussalem and the work is being carried out by Italian contractor Todini and local company Soroubat. The bidding process for the 100km highway from Gabes to Medenine is now being opened, while bidding for the 92km road from Medenine to the Libyan border outpost of Ras Jedir opened in October 2012. Bids for the construction of the 61km of peripheral roads
  • 3M and 407 ETR have it taped on a major motorway near Toronto
    August 1, 2019
    Canadian motorway concessionaire 407 ETR, in partnership with 3M Canada, is testing 3M's pavement marking tapes for Advanced Driver Assistance Systems on 2.5km of lanes. The initiative is part of the 407 ETR Living Labs programme of innovation to promote safety and next-generation transportation along the 140km route that opened in 1997 and was extended last year. King's Highway 407 is a tolled 400-series highway in the province of Ontario comprising a privately leased segment and publicly owned segm
  • Brine spraying can boost winter road safety and cut materials costs
    February 16, 2015
    A study on the use of a brine sprayer on the A8 Autobahn in Germany has yielded valuable data - *Jo Rommeswinkel writes. Since 2007, Autobahnplus Services (a+S) has been providing the operation and maintenance services on the 52km concession Autobahn A8 between Munich and Augsburg in Bavaria, a region renowned for its severe winter maintenance conditions. The Munich Augsburg section comprises 48km of six-lane dual carriageway and 4km of four-lane dual carriageway. Part of the road surface consists of low-no
  • Bogota transport infrastructure boost
    April 26, 2016
    The Colombian Government is investing in road infrastructure development, with a large portion of the budget being directed to Bogota. The road infrastructure programme includes 22 projects that will help cut chronic congestion in Colombian capital Bogota. Construction works for Avenida Longitudinal de Occidente (ALO) road expansion are expected to start in the first half of 2016. These will run from the Mondonedo intersection to Boyaca Avenue, in the southern part of the city. The budget for this project i