Upgrade for Medieval bridge

One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK. The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge.
February 29, 2012 Read time: 2 mins
Bideford Longbridge, the 24-span medieval masonry spans 190m over the River Torridge
One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor 3416 Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK.

The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge. Each span varies from 6.5m to 11m, and this is thought to be because the masonry bridge was built around the original timber bridge whose spans were dictated by the length of timber available at the time. During its lifetime the bridge has been widened a number of times to accommodate the changing nature and density of traffic flows. The last widening was completed in 1928 when reinforced concrete cantilever sections were added to each side of the masonry arches.

Following a structural assessment in 2006, Devon County Council identified 21 weakened cantilevers and the onset of corroding steel reinforcement, caused as a result of high chloride levels and lack of concrete cover. A 3tonne weight restriction was applied while various long term renovation solutions to safeguard the bridge were considered.

CRL was awarded the council contract to repair the concrete cantilevers in September 2008. The £2m project (E2.34 million) is particularly testing due to the combination of ICCP anode systems comprising mixed metal oxide coated titanium mesh and discrete mixed metal oxide coated titanium tubular anodes to ensure a uniform current distribution.

At the same time, the partial demolition and reconstruction of reinforced concrete elements is being carried out and a new underbridge lighting system is being installed, all of which is taking place from restricted scaffold access and in a tidal environment. The project is scheduled for completion in October 2009.

For more information on companies in this article

Related Content

  • US city of Vancouver approves new I-5 bridge
    July 18, 2022
    Vancouver in the US state of Washington and Portland in the state of Oregon are aiming for a new road bridge with the possibility of accommodating light rail transport.
  • Repair, recycling and warm mix technology at Italy’s Asphaltica exibition
    May 15, 2017
    As the name might suggest, the Asphaltica show in Verona, Italy was a good place to catch up on new ideas and applications for bitumen technology. Kristina Smith picked out a few highlights. Like many of its European neighbours, much of Italy’s road network is in dire need of love and attention. This was a constant theme for the Asphaltica show which was held alongside SaMoTer in Verona from 22-25 February. Speaking at the opening ceremony for the two shows, Michele Turrini, president of SITEB, which repres
  • Piling starts in Parkes for bypass project
    October 20, 2023
    Two new bridges are part of the US$120 million Parkes Bypass Project in the Australian state of New South Wales.
  • Aggregate Industries Lytag concrete reduces weight of Acton Bridge
    August 10, 2018
    The 84-year-old Acton Swing Bridge in the UK recently underwent a major renovation that included the use of Aggregates Industries’ Lytag lightweight concrete. The bridge - cared for by the Canal & River Trust, a charity operating in England and Wales - carries the busy A49 road over the River Weaver Navigation canal, near Cheshire in England. The €1.7 million complete refurbishment included strengthening the underside of the bridge as well as improvements to its appearance. Core to the project’s success