Upgrade for Medieval bridge

One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK. The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge.
February 29, 2012 Read time: 2 mins
Bideford Longbridge, the 24-span medieval masonry spans 190m over the River Torridge
One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor 3416 Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK.

The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge. Each span varies from 6.5m to 11m, and this is thought to be because the masonry bridge was built around the original timber bridge whose spans were dictated by the length of timber available at the time. During its lifetime the bridge has been widened a number of times to accommodate the changing nature and density of traffic flows. The last widening was completed in 1928 when reinforced concrete cantilever sections were added to each side of the masonry arches.

Following a structural assessment in 2006, Devon County Council identified 21 weakened cantilevers and the onset of corroding steel reinforcement, caused as a result of high chloride levels and lack of concrete cover. A 3tonne weight restriction was applied while various long term renovation solutions to safeguard the bridge were considered.

CRL was awarded the council contract to repair the concrete cantilevers in September 2008. The £2m project (E2.34 million) is particularly testing due to the combination of ICCP anode systems comprising mixed metal oxide coated titanium mesh and discrete mixed metal oxide coated titanium tubular anodes to ensure a uniform current distribution.

At the same time, the partial demolition and reconstruction of reinforced concrete elements is being carried out and a new underbridge lighting system is being installed, all of which is taking place from restricted scaffold access and in a tidal environment. The project is scheduled for completion in October 2009.

For more information on companies in this article

Related Content

  • Treating Russia’s bridges
    April 11, 2013
    Russia is home to all of the world’s climatic zones and to over 6,000 bridges. Rain and wind, sun and heat, snow and ice mean that the Russian weather is extreme, and because its bridges need special protection their structural elements are insulated with bituminous sheeting. Evonik says that temperature stability and long life are key criteria for selecting insulating materials, and this has led to an increase in the use of special sheeting, some of which has been modified with its Vestoplast product. Ove
  • Morandi Bridge investigation continuing
    February 1, 2019
    The investigation into the collapse of the Morandi Bridge in the Italian city of Genoa is continuing. The failure of the bridge in August 2018 resulted in 43 fatalities. A central section of the structure collapsed and most of the deaths were of those crossing in vehicles at the time, although the deaths also included those hit by falling debris underneath. A number of engineers and managers with responsibilities relating to the bridge are now being investigated directly. The investigators are also looking
  • Concrete runway surface for Indonesian airport
    May 14, 2020
    The new Yogyakarta International Airport in Indonesia is seeing the benefit of a high-quality runway surface. The runway was built quickly and efficiently to a high standard, using the latest equipment. In all, 11 slipform pavers from Wirtgen played a key role in the airport’s construction.
  • Texas highway project tackles congestion
    April 10, 2012
    A new highway project in Texas will tackle peak congestion