Upgrade for Medieval bridge

One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK. The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge.
February 29, 2012 Read time: 2 mins
Bideford Longbridge, the 24-span medieval masonry spans 190m over the River Torridge
One of the most demanding and challenging impressed current cathodic protection (ICCP) projects ever undertaken by specialist main contractor 3416 Concrete Repairs Ltd (CRL) is being carried out on Bideford Longbridge in County Devon, UK.

The 24-span medieval masonry arch bridge spans 190m over the tidal estuary of the River Torridge. Each span varies from 6.5m to 11m, and this is thought to be because the masonry bridge was built around the original timber bridge whose spans were dictated by the length of timber available at the time. During its lifetime the bridge has been widened a number of times to accommodate the changing nature and density of traffic flows. The last widening was completed in 1928 when reinforced concrete cantilever sections were added to each side of the masonry arches.

Following a structural assessment in 2006, Devon County Council identified 21 weakened cantilevers and the onset of corroding steel reinforcement, caused as a result of high chloride levels and lack of concrete cover. A 3tonne weight restriction was applied while various long term renovation solutions to safeguard the bridge were considered.

CRL was awarded the council contract to repair the concrete cantilevers in September 2008. The £2m project (E2.34 million) is particularly testing due to the combination of ICCP anode systems comprising mixed metal oxide coated titanium mesh and discrete mixed metal oxide coated titanium tubular anodes to ensure a uniform current distribution.

At the same time, the partial demolition and reconstruction of reinforced concrete elements is being carried out and a new underbridge lighting system is being installed, all of which is taking place from restricted scaffold access and in a tidal environment. The project is scheduled for completion in October 2009.

For more information on companies in this article

Related Content

  • Innovative, quality asphalt surfacing solutions
    February 22, 2012
    An array of innovative mix designs and special processes have been introduced to the paving market in recent years. These are now being used in many site applications and are offering contractors the benefits of fast application and high surface quality while providing safe, cost-effective and hard wearing solutions with long life for clients.
  • Poland's A1 motorway progressing well
    February 9, 2012
    The second major phase of a north-south motorway in Poland is well underway. It will reduce congestion and improve safety as Patrick Smith reports Before the whistle blows to herald the start of Euro 2012, Poland's main seaport Gdansk will boast new roads, a new airport and a new stadium. The historic city in the north of the country on the Baltic coast will be one of the venues for football's 14th European Championship, being co-hosted by Poland and Ukraine.
  • 2023 Global Road Achievement Award Winner - Environmental Mitigation: Xingyi Ring Expressway
    March 6, 2024
    An important road link in China has won a prestigious 2023 Global Road Achievement Award
  • Brine spraying can boost winter road safety and cut materials costs
    February 16, 2015
    A study on the use of a brine sprayer on the A8 Autobahn in Germany has yielded valuable data - *Jo Rommeswinkel writes. Since 2007, Autobahnplus Services (a+S) has been providing the operation and maintenance services on the 52km concession Autobahn A8 between Munich and Augsburg in Bavaria, a region renowned for its severe winter maintenance conditions. The Munich Augsburg section comprises 48km of six-lane dual carriageway and 4km of four-lane dual carriageway. Part of the road surface consists of low-no