Ulma uses its CVS Cantilever Formwork Carriage over the Odra

A second Odra River bridge in Cigacice is the last stage of work for a section of the S3 expressway in Poland’s Lubuskie township. The bridge is part of the S3 route between Sulechów to Nowa Sól and is expected to be completed by year’s end.
February 11, 2020 Read time: 2 mins
Poland’s MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS

As in the case of the parallel MS-4A bridge, the MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS. Ulma says that its carriages offer significant weight-bearing capacity without any compromise in their ability to adapt to varied cross-sections. In the case of spans located above the ground, the incremental launching method was used.

For the span using the balanced cantilever method, the pier caps were built using the universal formwork system Enkoform HMK in combination with T-60 Frame Shoring Towers. Regardless of the construction method, Enkoform HMK adjusted perfectly to the varied deck width along its entire length, according to Ulma.

To build the spans over the river, Ulma designed and delivered four CVS 200/5 form carriers which allows the pouring of segments up to 300tonnes.

For this part of the MS-4B, sections measuring 4.45m-long were completed in seven days. The form carriers are made using standard components from the universal MK System, making it a simple task to adjust both the formwork and form carrier structures to the geometry of the bridge.

Standardising the CVS form carrier with the MK System allows for substantial cost savings. Once the project is completed, the majority of the components can be reused in a multitude of structures.

To guarantee safe areas, the form carrier had working platforms at every level. The platforms, designed with BRIO Modular Scaffolding components, were set on the truss at the front of the carrier along with the suspended formwork. This guaranteed employee safety while working with the formwork at the back of the carrier.

Each carrier is equipped with a hydraulic system used to advance, level and anchor it. The use of a wide range of hydraulic systems allowed for the effective and safe advance of the formwork structure.

For more information on companies in this article

Related Content

  • Ambitious road tunnelling projects around the world
    November 29, 2013
    The construction of the world’s longest subsea road tunnel in Norway and a vital new link under the Bosphorus Strait in Turkey are among a host of exciting, major road tunnel-based projects currently being undertaken across the globe. Guy Woodford reports Sandvik DTi series tunnelling jumbos are being used for the excavation of Solbakktunnel, set to become the world’s longest subsea road tunnel.
  • Bridge deck launched for the New Wear Crossing, Sunderland (Video)
    March 30, 2017

    The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

    The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

  • Tanzania’s work on East Africa’s multi-national road project
    November 28, 2022
    Tanzania is kick-starting construction work on the missing link in East Africa's multinational road
  • Bolivia’s new highway
    October 10, 2017
    Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia. The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the European Investment