Ulma uses its CVS Cantilever Formwork Carriage over the Odra

A second Odra River bridge in Cigacice is the last stage of work for a section of the S3 expressway in Poland’s Lubuskie township. The bridge is part of the S3 route between Sulechów to Nowa Sól and is expected to be completed by year’s end.
February 11, 2020 Read time: 2 mins
Poland’s MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS

As in the case of the parallel MS-4A bridge, the MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS. Ulma says that its carriages offer significant weight-bearing capacity without any compromise in their ability to adapt to varied cross-sections. In the case of spans located above the ground, the incremental launching method was used.

For the span using the balanced cantilever method, the pier caps were built using the universal formwork system Enkoform HMK in combination with T-60 Frame Shoring Towers. Regardless of the construction method, Enkoform HMK adjusted perfectly to the varied deck width along its entire length, according to Ulma.

To build the spans over the river, Ulma designed and delivered four CVS 200/5 form carriers which allows the pouring of segments up to 300tonnes.

For this part of the MS-4B, sections measuring 4.45m-long were completed in seven days. The form carriers are made using standard components from the universal MK System, making it a simple task to adjust both the formwork and form carrier structures to the geometry of the bridge.

Standardising the CVS form carrier with the MK System allows for substantial cost savings. Once the project is completed, the majority of the components can be reused in a multitude of structures.

To guarantee safe areas, the form carrier had working platforms at every level. The platforms, designed with BRIO Modular Scaffolding components, were set on the truss at the front of the carrier along with the suspended formwork. This guaranteed employee safety while working with the formwork at the back of the carrier.

Each carrier is equipped with a hydraulic system used to advance, level and anchor it. The use of a wide range of hydraulic systems allowed for the effective and safe advance of the formwork structure.

For more information on companies in this article

Related Content

  • Turkey’s important new tunnel will improve transport links
    May 18, 2016
    Major advances in tunnelling will allow cars to travel underneath the Bosphorus sea channel in Turkey's Istanbul next year when its third road link is opened, writes Adrian Greeman. The Bosphorus is redolent with history and strategic significance. As one of the world's most significant sea connections, linking the landlocked Black Sea to the Marmara Sea and the Mediterranean beyond, it has been vitally important for trade and crucial for military access. It is also one of the biggest obstacles for land tra
  • Complete control of machines using technology
    December 12, 2019
    Sophisticated machine control technology has been utilised on heavy equipment to help deliver a challenging project in New Zealand
  • Italy's new southern highway route
    May 13, 2021
    An important new highway route is currently under construction in South Italy
  • Major upgrade for Chicago O’Hare Airport
    August 14, 2015
    Internationally, airports are being upgraded and expanded to increase capacity and safety – Mike Woof writes. All around the world, airports are being expanded and upgraded, both to cope with massive increases in passenger numbers and also to handle larger aircraft. Runways have to be rebuilt with stronger structures and surfaces to handle greater air traffic volumes as well as increased loads from larger aeroplanes. Building airport runways, however, poses many challenges for construction crews. Paving qua