Ulma uses its CVS Cantilever Formwork Carriage over the Odra

A second Odra River bridge in Cigacice is the last stage of work for a section of the S3 expressway in Poland’s Lubuskie township. The bridge is part of the S3 route between Sulechów to Nowa Sól and is expected to be completed by year’s end.
February 11, 2020 Read time: 2 mins
Poland’s MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS

As in the case of the parallel MS-4A bridge, the MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS. Ulma says that its carriages offer significant weight-bearing capacity without any compromise in their ability to adapt to varied cross-sections. In the case of spans located above the ground, the incremental launching method was used.

For the span using the balanced cantilever method, the pier caps were built using the universal formwork system Enkoform HMK in combination with T-60 Frame Shoring Towers. Regardless of the construction method, Enkoform HMK adjusted perfectly to the varied deck width along its entire length, according to Ulma.

To build the spans over the river, Ulma designed and delivered four CVS 200/5 form carriers which allows the pouring of segments up to 300tonnes.

For this part of the MS-4B, sections measuring 4.45m-long were completed in seven days. The form carriers are made using standard components from the universal MK System, making it a simple task to adjust both the formwork and form carrier structures to the geometry of the bridge.

Standardising the CVS form carrier with the MK System allows for substantial cost savings. Once the project is completed, the majority of the components can be reused in a multitude of structures.

To guarantee safe areas, the form carrier had working platforms at every level. The platforms, designed with BRIO Modular Scaffolding components, were set on the truss at the front of the carrier along with the suspended formwork. This guaranteed employee safety while working with the formwork at the back of the carrier.

Each carrier is equipped with a hydraulic system used to advance, level and anchor it. The use of a wide range of hydraulic systems allowed for the effective and safe advance of the formwork structure.

For more information on companies in this article

Related Content

  • Polish debut
    July 20, 2012
    PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642
  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of
  • Interchange project wins major engineering award
    December 11, 2015
    The Section 5 Palmetto SR826/836 Interchange project in Florida has won the 2016 FICE Engineering Excellence Grand Award in the Structures category.