Ulma uses its CVS Cantilever Formwork Carriage over the Odra

A second Odra River bridge in Cigacice is the last stage of work for a section of the S3 expressway in Poland’s Lubuskie township. The bridge is part of the S3 route between Sulechów to Nowa Sól and is expected to be completed by year’s end.
February 11, 2020 Read time: 2 mins
Poland’s MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS

As in the case of the parallel MS-4A bridge, the MS-4B bridge is being constructed using the balanced cantilever formwork carriage CVS. Ulma says that its carriages offer significant weight-bearing capacity without any compromise in their ability to adapt to varied cross-sections. In the case of spans located above the ground, the incremental launching method was used.

For the span using the balanced cantilever method, the pier caps were built using the universal formwork system Enkoform HMK in combination with T-60 Frame Shoring Towers. Regardless of the construction method, Enkoform HMK adjusted perfectly to the varied deck width along its entire length, according to Ulma.

To build the spans over the river, Ulma designed and delivered four CVS 200/5 form carriers which allows the pouring of segments up to 300tonnes.

For this part of the MS-4B, sections measuring 4.45m-long were completed in seven days. The form carriers are made using standard components from the universal MK System, making it a simple task to adjust both the formwork and form carrier structures to the geometry of the bridge.

Standardising the CVS form carrier with the MK System allows for substantial cost savings. Once the project is completed, the majority of the components can be reused in a multitude of structures.

To guarantee safe areas, the form carrier had working platforms at every level. The platforms, designed with BRIO Modular Scaffolding components, were set on the truss at the front of the carrier along with the suspended formwork. This guaranteed employee safety while working with the formwork at the back of the carrier.

Each carrier is equipped with a hydraulic system used to advance, level and anchor it. The use of a wide range of hydraulic systems allowed for the effective and safe advance of the formwork structure.

For more information on companies in this article

Related Content

  • Bridges in Sunderland and Poland are being slid into place
    February 6, 2017
    Sunderland sees a bridge slide into place and two bridges inch their way across a Polish highway Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation likely to take place next year. The project to build the New Wear Crossing is now halfway through with the first half of the steel deck b
  • ULMA bridges the Danube and Kayak rivers
    March 16, 2021
    The D4 motorway and R7 expressway project is Slovakia’s largest public-private partnership.
  • Extra work for Ulma on Ireland’s New Ross extradosed bridge
    September 19, 2019
    ULMA has taken part in construction Ireland’s New Ross, the longest extradosed bridge in the world. The €230 million project includes a 14km dual carriageway and a three-tower 900m-long extrados bridge over the Barrow River between Pink Point and Strokestown – to be open in early 2020 – that bypasses the town of New Ross. The extradosed bridge is characterised by its cables set at lower angles, meaning that pylons are shorter in relation to deck span lengths. ULMA was responsible for the transverse s
  • Mexico viaduct complete with ULMA formwork
    February 9, 2018
    ULMA developed a comprehensive solution for the construction project of the Interlomas Viaduct, México. Forming part of Mexico City’s transportation infrastructure development plan, this viaduct is 227m long and connects the residential and commercial area Interlomas with the Naucalpan-Toluca highway. ULMA designed a solution fully tailored to meet the pace and needs of the client: gantry falsework for two 59m outer spans, and a CVS Form Carrier for the central span of 108m. ULMA’s engineering team combi