ULMA engineering solutions on the emblematic Arch of Innovation bridge, Brazil

The arch of innovation is a cable-stayed bridge that will connect Zarur, São João, and Cassiano Ricardo avenues in São Paulo, Brazil. With a height of 100m, it has become one of the most iconic bridges in the country of its type, given its peculiar arc shape.
June 21, 2020 Read time: 3 mins

 

This bridge will create a safer and faster route for more than 180,000 vehicles/day, which will ease Sao Paulo's traffic. It will also include a bicycle lane of more than 3.6km.

One of the most relevant requirements in this project has been the versatility of the systems and the safety of the operators. To this end, the engineering team developed an integrated solution with the ideal formwork and scaffolding systems and applications for the pylons and the roads that run between them. The Queiroz Galvão construction company has once again trust in ULMA's engineering solutions, as well as in the capacity to respond to a project with stringent execution deadlines.

ULMA pic2The ATR self-climbing system was chosen for the two pylons with variable inclination and four-sided section, in combination with the VMK timber-beam formwork for the outside and the KSP platform for the inside. The self-climbing system has been perfectly adapted to the inclination and elliptical curve of the shaft of up to 23º in the last concreting. The whole set has allowed high execution rates, three-day concreting cycles in 3.6m high sections, without the need for a crane. In addition, it has three levels of working platforms for carrying out work on the formwork, rebar or concrete, as well as for lifting the structure, maintaining strict safety levels at great heights at all times. The platforms were designed in such a way that it was possible to regulate the angle to maintain horizontality as the arch progressed.  Despite the complexity of the geometry, the MK system has solved all the structural requirements.

With regard to productivity, the use of self-climbing formwork halves working times compared to a conventional climbing system in this type of project. This is because the system requires less handling. As the movement is carried out using a hydraulic system, there is minimal use of the crane, which is freed up for other tasks.

The two carriageways rest on an X shape. They were built with ENKOFORM HMK, supported by T-60 shoring towers. A solution of MK gantry formwork was proposed for the rest of the board to avoid closing the tracks.

For the construction of the arch section of the bridge, a supporting structure made of MK and VM beams supported by T-60 shoring systems was constructed. Custom metal profiles bear all the weight of the T-60 shoring system.

To access the different areas of the bridge, BRIO stairs were enabled on each side of the arch and in two separate sections. The first section is 60m-high and rests on the ground. The second section, 40m-high, consists of three independent staircases arranged on BMK consoles on the arch.

Constructor: QUEIROZ GALVÃO CONSTRUCTION COMPANY.


Sponsored content produced in association with ULMA Construction

For more information on companies in this article

Related Content

  • Innovative formwork beats bridge design challenges
    February 14, 2012
    Companies are coming up with innovative formwork solutions to overcome "challenging" designs for bridges. Patrick Smith reports
  • Formwork plays a leading role in global infrastructure projects
    June 13, 2012
    New and highly regarded existing formwork systems have been used in major recent transport-related construction projects across the globe. Guy Woodford looks at some of their applications The multi-million dollar Mississippi River Bridge project in the United State is creating a vital new gateway between Illinois and Missouri. Central to the project is the realignment and reconstruction of Interstate 70 and a new landmark bridge, featuring two pylons projecting vertically from the Mississippi river bed w
  • Qatar tunnel project benefits from sophisticated formwork
    March 7, 2018
    A sophisticated formwork solution has played an important part in the construction of a new road and rail tunnel in Qatar in the Middle East. The formwork system was supplied by ULMA, which supplied its equipment for the construction of the Lusail Boulevard Tunnel in Qatar. The new tunnel provides access to the new Lusail City Development, from the heart of Doha and will be a vital transport link for the planned 2022 FIFA World Cup tournament. The overall Lusail City Development, located 15km north of Do
  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson