Terex Superlift 3800 crawler crane lifts Schoneck Bridge into place

The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its Terex Superlift 3800 lattice boom crawler crane to complete the project. Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconn
January 4, 2016 Read time: 2 mins
Terex crane helps lift in new bridge in Germany
The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its 1222 Terex Superlift 3800 lattice boom crawler crane to complete the project.

Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconnected before the lifts were done. To avoid disruption to the train service, we had a window of only a few hours in both cases,” said Martin Mittler, one of the Steil managers for the project.

The work site was also in a residential area, a tight space for the 19 trucks delivering the Superlift 3800 crane’s components on site and setting it up with the Terex assist crane.

“The modular quick-connect system makes it possible to split the crane’s basic structure into two parts, one reason why the Superlift was chosen,” said Mittler. It was set up in two days in an LH1 configuration with a 42m main boom, 205tonnes of superstructure counterweight and 50tonnes of central ballast. The unstable working area for the crane had to be prepared with red ironwood crane mats to bear the machine’s weight.

The bridge structure was delivered in two sections and welded on-site, weighing in total 70tonnes, including slinging gear. After the load was meticulously rigged for balance, power to the overhead lines was turned off and the lift started.

The operator lifted the bridge, which was rigged at four attachment points, to a height of 6m at a working radius of 26m, in order to swing it over the tracks.

The working radius was increased to around 30m by lowering the boom and moving it forward with the Superlift by about 1m. The bridge was set down on supports with laser-like precision.

The tail end of the lift also went smoothly. Then, in just ten hours, the Superlift 3800 was disassembled and ready to truck to its next job.

For more information on companies in this article

Related Content

  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi
  • Danube bridge takes shape
    February 10, 2012
    A new bridge over the River Danube between Bulgaria and Romania is expected to benefit to the economies of both nations. Krasimir Krastanov reports
  • Grove unveils GRT655 rough-terrain crane
    March 10, 2017
    The new Grove GRT655 rough-terrain crane includes features most commonly associated with much larger cranes. The crane was unveiled at CONEXPO-CON/AGG 2017 on Tuesday. “We have loaded the GRT655 with features that companies usually see on cranes in larger capacity classes,” said Paul Cutchall, product manager for rough-terrain cranes at Manitowoc, which operates Grove.