Tensar’s Spectra Pavement Optimisation system at work in Durham

Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England. The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale
August 3, 2017 Read time: 3 mins
Tensar’s Spectra Pavement Optimisation system incorporates TriAx geogrid
340 Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England.

The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale-up to manufacture on site.

Tensar’s Spectra Pavement Optimisation system, incorporating TriAx geogrid, has mechanically stabilised the roads’ granular layers, enabling them to be built over the site’s weak and variable ground. The system mitigates the risk of differential settlement and reduces the amount of imported material.

“The TriAx interacted with the aggregate to create a mechanically stabilised layer, which increased flexural rigidity and allowed the total pavement thickness to be reduced,” said Craig Andrews, Tensar’s highways manager.

“The granular particles partially penetrate through the geogrid apertures, which confines and restrains the stone from moving both vertically and laterally. This helps to deliver road pavements capable of carrying anticipated traffic loads.”

Tensar worked closely with 1284 Durham County Council to develop the initial pavement design for the roads, which was adjusted once the CBRs were taken. On-site California Bearing Ratio – CBR - tests are used for evaluation and design of flexible pavement components such as base and subbase course and subgrades and for other applications (such as unsurfaced roads) for which CBR is the desired strength parameter.

“Because ground conditions are so varied, we finalised the optimal pavement design as the underlying ground was exposed and tested,” Andrews said.

This approach meant that, rather than using a one-size-fits-all design to cope with the weakest ground, thicker pavements could be used in these areas, while thinner sections could be used over stronger ground. As a result, material use was reduced and construction was faster and more cost-effective.

“We used three mechanically stabilised layers above the very weak ground, reducing this to two layers over slightly improved areas,” said Andrews. “Where ground conditions were more favourable, we were able to design the capping layer out completely and only a single mechanically stabilised layer was needed.”

A total of 10,000m² of TriAx was laid at NETPark by Durham-based Groundwork Services, which was working on behalf of main contractor ESH Group.

Tensar manufactures subgrade stabilisation and soil reinforcement solutions, including high-performance geogrid and geotextile products used in road, rail and other infrastructure.

For more information on companies in this article

Related Content

  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • No compromise with FAE’s STABI/H stabiliser
    May 5, 2021
    The STABI/H is FAE's top-of-the-line professional stabiliser for the construction market.
  • Road repairs take to the air
    November 29, 2018
    Automated road repairs using 3D printing could save money and reduce disruption, reports Kristina Smith It’s the middle of the night and in the street below a team is busy carrying out repairs to the road surface. But there isn’t a human in sight. A road-repair drone has landed at the site of a crack and a 3D asphalt printer is now busy filling in that crack. A group of traffic cone drones have positioned themselves around the repair location to protect the repair drone and divert traffic around it.
  • New truck parking facilities for major UK route
    May 26, 2016
    Contractor Balfour Beatty is to construct new truck parking facilities alongside the M20 motorway in Kent in the UK. The package of works was awarded by Highways England and the £130 million deal covers the development of the proposals during the Early Contractor Involvement (ECI) phase of the project. This deal also includes the construction of the lorry area subject to a decision to proceed from the UK Government. The £250 million truck parking area was initially announced by the UK’s Chancellor of the Ex