Tensar’s Spectra Pavement Optimisation system at work in Durham

Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England. The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale
August 3, 2017 Read time: 3 mins
Tensar’s Spectra Pavement Optimisation system incorporates TriAx geogrid
340 Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England.

The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale-up to manufacture on site.

Tensar’s Spectra Pavement Optimisation system, incorporating TriAx geogrid, has mechanically stabilised the roads’ granular layers, enabling them to be built over the site’s weak and variable ground. The system mitigates the risk of differential settlement and reduces the amount of imported material.

“The TriAx interacted with the aggregate to create a mechanically stabilised layer, which increased flexural rigidity and allowed the total pavement thickness to be reduced,” said Craig Andrews, Tensar’s highways manager.

“The granular particles partially penetrate through the geogrid apertures, which confines and restrains the stone from moving both vertically and laterally. This helps to deliver road pavements capable of carrying anticipated traffic loads.”

Tensar worked closely with 1284 Durham County Council to develop the initial pavement design for the roads, which was adjusted once the CBRs were taken. On-site California Bearing Ratio – CBR - tests are used for evaluation and design of flexible pavement components such as base and subbase course and subgrades and for other applications (such as unsurfaced roads) for which CBR is the desired strength parameter.

“Because ground conditions are so varied, we finalised the optimal pavement design as the underlying ground was exposed and tested,” Andrews said.

This approach meant that, rather than using a one-size-fits-all design to cope with the weakest ground, thicker pavements could be used in these areas, while thinner sections could be used over stronger ground. As a result, material use was reduced and construction was faster and more cost-effective.

“We used three mechanically stabilised layers above the very weak ground, reducing this to two layers over slightly improved areas,” said Andrews. “Where ground conditions were more favourable, we were able to design the capping layer out completely and only a single mechanically stabilised layer was needed.”

A total of 10,000m² of TriAx was laid at NETPark by Durham-based Groundwork Services, which was working on behalf of main contractor ESH Group.

Tensar manufactures subgrade stabilisation and soil reinforcement solutions, including high-performance geogrid and geotextile products used in road, rail and other infrastructure.

For more information on companies in this article

Related Content

  • Geosynthetics stabilise differential settlement
    May 3, 2012
    The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and
  • Geosynthetics stabilise differential settlement
    March 14, 2012
    The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and
  • Tensar International to open new plant in Russia by January 2014
    November 20, 2012
    Tensar International is building a manufacturing plant in Russia. Tensar is the majority shareholder in the joint venture, with remaining investment coming from Russian partners. Don Meltzer, chief executive of US parent company, Tensar Corporation; and Bob Vevoda, chief operating officer and president of Tensar International; met with their Russian JV partners in London earlier this month to finalise the funding and construction schedule.
  • Tensar wins Chinese patent cases
    April 30, 2012
    International ground stabilisation specialist, Tensar has successfully defended its TriAx product range against several Chinese patent infringements.The TriAx geogrid, patented in many countries around the world by Tensar for use in ground stabilisation, road, rail and other applications, has received many awards for innovation and has achieved considerable commercial success since its introduction a few years ago.