Skip to main content

Tensar’s Spectra Pavement Optimisation system at work in Durham

Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England. The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale
August 3, 2017 Read time: 3 mins
Tensar’s Spectra Pavement Optimisation system incorporates TriAx geogrid
340 Tensar’s flexible and reactive approach to optimising pavement design has delivered cost savings on a project to expand a science and technology park in England.

The US$6.7 million NETPark Phase 3A Infrastructure project in county Durham will see construction of a spine road and side roads. The road will open up 10.5ha of development land at the North East Technology Park. The ambitious expansion plans will create additional space for research and development companies which need room to prototype and scale-up to manufacture on site.

Tensar’s Spectra Pavement Optimisation system, incorporating TriAx geogrid, has mechanically stabilised the roads’ granular layers, enabling them to be built over the site’s weak and variable ground. The system mitigates the risk of differential settlement and reduces the amount of imported material.

“The TriAx interacted with the aggregate to create a mechanically stabilised layer, which increased flexural rigidity and allowed the total pavement thickness to be reduced,” said Craig Andrews, Tensar’s highways manager.

“The granular particles partially penetrate through the geogrid apertures, which confines and restrains the stone from moving both vertically and laterally. This helps to deliver road pavements capable of carrying anticipated traffic loads.”

Tensar worked closely with 1284 Durham County Council to develop the initial pavement design for the roads, which was adjusted once the CBRs were taken. On-site California Bearing Ratio – CBR - tests are used for evaluation and design of flexible pavement components such as base and subbase course and subgrades and for other applications (such as unsurfaced roads) for which CBR is the desired strength parameter.

“Because ground conditions are so varied, we finalised the optimal pavement design as the underlying ground was exposed and tested,” Andrews said.

This approach meant that, rather than using a one-size-fits-all design to cope with the weakest ground, thicker pavements could be used in these areas, while thinner sections could be used over stronger ground. As a result, material use was reduced and construction was faster and more cost-effective.

“We used three mechanically stabilised layers above the very weak ground, reducing this to two layers over slightly improved areas,” said Andrews. “Where ground conditions were more favourable, we were able to design the capping layer out completely and only a single mechanically stabilised layer was needed.”

A total of 10,000m² of TriAx was laid at NETPark by Durham-based Groundwork Services, which was working on behalf of main contractor ESH Group.

Tensar manufactures subgrade stabilisation and soil reinforcement solutions, including high-performance geogrid and geotextile products used in road, rail and other infrastructure.

For more information on companies in this article

Related Content

  • Advances in bitumen technology: new applications
    February 16, 2022
    This month, we look at four very different pavement technologies in four very different applications
  • Ground penetrating radar used to investigate tunnel deterioration
    May 13, 2015
    Using ground penetrating radar to determine reason for serious pavement settling in Kentucky-Tennessee tunnel Just a few years after the opening of the Cumberland Gap Tunnel, highway officials noticed moderate to severe settling of the continuously reinforced concrete pavement. The mountain tunnel provides an important link between Kentucky and Tennessee along US25E and the problem looked serious, with many voids discovered beneath the pavement surface. To investigate the problems, the Kentucky Transpor
  • New methods for non-destructive concrete testing
    August 29, 2017
    How best is it possible to assess the state of concrete in a road pavement, bridge deck or tunnel wall? One of the most reliable ways is to take a core of concrete from the structure to analyse and test in the laboratory. One downside to this method is that doing the test creates weak points in the structure that must then be repaired. Another is that the frequency of such cores cannot be too great – so it is possible that some problem areas will be missed. New technologies from the world of geospatial eng
  • Polymer enhanced bitumen technology improves performance
    July 11, 2012
    As overall traffic volumes increase, the contribution from commercial vehicles with increased axle loads is growing, putting ever more strain on roads and highway maintenance budgets. Highway authorities are looking for products that will be able to cope better and are more cost effective over the life of a road. Technical innovation is the only way to answer this challenge effectively, says BP Bitumen, one of a number of specialist companies involved in bitumen technology.