Swiss roundabout goes underground

The Swiss, well-known for their tunnel constructions, have enhanced their reputation with the recent Gotthard Tunnel breakthrough which has created the world's longest tunnel. And in Bern, a roundabout is being re-positioned almost 10m under the ground, which will transform a somewhat dismal road intersection into an attractive gateway to the country's capital. PERI provided a comprehensive formwork solution for the realisation of the massive beams, reinforced concrete slab along with the conically-sh
February 7, 2012 Read time: 4 mins
In Bern, Switzerland, PERI provided a comprehensive formwork solution to help construct an underground roundabout
The Swiss, well-known for their tunnel constructions, have enhanced their reputation with the recent Gotthard Tunnel breakthrough which has created the world's longest tunnel.

And in Bern, a roundabout is being re-positioned almost 10m under the ground, which will transform a somewhat dismal road intersection into an attractive gateway to the country's capital.

298 PERI provided a comprehensive formwork solution for the realisation of the massive beams, reinforced concrete slab along with the conically-shaped roundabout walls, which are to be formed in architectural concrete.

Over 65,000 vehicles pass through the junction on a daily basis, and being located near the motorway, traffic is reduced to a snail's pace, resulting in long waiting times for drivers; a negative impact on the environment and badly affecting the public transport system.

The Wankdorfplatz is being transformed into a two-storey structure, meaning a project from an ideas competition is fast becoming a reality.

From 2012 onwards, the underground roundabout with a 50m diameter will accelerate the flow of traffic and create space for pedestrians and cyclists above ground as well as greatly improving bus and tram connections.

For the pre-stressed beams and reinforced concrete slab as well as for the conically-shaped walls in architectural concrete quality, PERI's Swiss engineers developed various formwork solutions using mainly rentable system equipment which matched the requirements of the contractor.

The customised wall formwork elements for the curved external walls of the roundabout area were prefabricated by PERI on the basis of the VARIO GT 24 girder wall formwork system. For this project, the radii range from 30m to 45m with a wall inclination of 10:1.

The construction of the 1.8m wide, pre-stressed beams with varying heights of between 1.15m and 2.7m took place on a combined load-bearing and working level which angled upwards to the centre of the roundabout. This was formed using the flexible MULTIFLEX girder slab formwork system with the help of GT 24 lattice girders as very high load-bearing twin main beams and VT 20 cross beams.

The MULTIPROP system served as support with towers comprising MRK frames connected to MULTIPROP aluminium slab props.

"Thanks to the free-running collar and the integrated measuring tape, these could be easily adjusted to suit the varying heights of between 5m and 6m. TRIO panel formwork also found use as the side formwork. By means of the double thickness formlining excellent concrete surfaces could be achieved," says PERI.

"Following this, four slab segments were to be constructed and connected to the crosswise-arranged beams. The extremely tight construction schedule meant that sufficient formwork materials were to be available on site for the complete slab area of some 1,400m². The up-to 1.2m thick reinforced concrete slab runs in a truncated cone-shaped manner with an approximate 3% gradient on the upper side. In addition, the underside of the slab features five height offsets and a number of different inclinations. In close cooperation with the contractor, PERI created a formwork concept for this which allowed safe and accurate positioning of the required additional special elements." MULTIPROP towers were again used as shoring. The MULTIFLEX girder slab formwork system formed a level intermediate platform which covered the entire area. In contrast to the beam solution with VT 20 cross girders, the use of GT 24 girders as radially-positioned cross beams proved to be the more cost-effective variant in order to reliably transfer the loads via GT 24 double main beams and MULTIPROP props. From this working level, the construction crew was able to quickly install the pre-fabricated special elements which had been put together in the PERI assembly hall.

Due to limited on site storage, PERI Switzerland delivered the formwork elements on a just-in-time basis.

For more information on companies in this article

Related Content

  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • VST used on Portuguese bridge
    February 17, 2012
    PERI says that its new VST heavy-duty shoring tower serves as load-bearing scaffold for the large bridge and civil engineering projects. Each leg on the VST (VARIOKIT Shoring Tower) system can carry a load of around 600kN (the weight of about 60 VW Golf cars or one Leopard-2 tank), and the extremely flexible modular system can be assembled as segmental sections, towers or shoring tower frames for heights up to 40m.
  • Qatar tunnel project benefits from sophisticated formwork
    March 7, 2018
    A sophisticated formwork solution has played an important part in the construction of a new road and rail tunnel in Qatar in the Middle East. The formwork system was supplied by ULMA, which supplied its equipment for the construction of the Lusail Boulevard Tunnel in Qatar. The new tunnel provides access to the new Lusail City Development, from the heart of Doha and will be a vital transport link for the planned 2022 FIFA World Cup tournament. The overall Lusail City Development, located 15km north of Do
  • Germany's advanced bridge construction
    February 24, 2012
    The A98 single-lane motorway in Germany is being extended by a second pair of lanes. Work began in 2007 and required building a second bridge at Rheinfelden in the south-west of the country, parallel to the existing bridge, and identical in design and construction.