Super job for a Demag CC 3800-1 without a Superlift counterweight

A Demag CC 3800-1 crane with an 84m-long main boom was recently set up in Germany without a Superlift counterweight to save space. The jobsite was the replacement of the old viaduct on the A45 Freeway that spans the Lahn River near Dorlar in Germany. Bietigheim-Bissingen-based crane service provider Wiesbauer solved the site’s space issues by using a Demag CC 3800-1. “This site required us to lift loads of 96-148tonnes at radii of 40-64m, so there was no option but to use a crawler crane in the 650tonne c
July 4, 2019 Read time: 4 mins
Demag CC 3800-1 lattice boom crawler crane on the A45 Freeway that spans the Lahn River near Dorlar, Gemrany
A Demag CC 3800-1 crane with an 84m-long main boom was recently set up in Germany without a Superlift counterweight to save space.


The jobsite was the replacement of the old viaduct on the A45 Freeway that spans the Lahn River near Dorlar in Germany. Bietigheim-Bissingen-based crane service provider Wiesbauer solved the site’s space issues by using a Demag CC 3800-1.

“This site required us to lift loads of 96-148tonnes at radii of 40-64m, so there was no option but to use a crawler crane in the 650tonne class despite the constrained space conditions,” said Marco Wilhelm, Wiesbauer project manager.

The company decided on the Demag CC 3800-1 lattice boom crawler crane, which was assisted by an AC 160-5 all-terrain crane - both from the manufacturer 1222 Terex. However, before the CC 3800-1 could be brought to the jobsite, its work area needed to be prepared first.

“The Lahn flows right along the work site, so the ground wouldn’t have been able to bear the heavy load exerted by our machine. That’s why the work area was prepared with a concrete foundation for the crane,” Wilhelm explained.

This made it possible to safely set up the crane with an LSL 1 configuration featuring an 84m main boom, 36m Superlift boom, 50tonne central ballast and 225tonne counterweight, with the counterweight in particular being absolutely crucial.

“The extremely heavy counterweight enabled us to set up the main boom without an additional Superlift counterweight. Moreover, this was what made it possible to use the enormous crawler crane to pick up the loads at such a tight work site, as leaving out the Superlift counterweight actually increased the crane’s usable working area significantly,” he said.

In fact, the Superlift counterweight was not needed until later during the lift.

Once the preparation work was done, the Wiesbauer team was ready to carry out all the lifts with the Demag CC 3800-1. To build the two bridge sections, it was necessary to perform the work in two steps at two different work areas. The steel components had to be lifted over the Lahn river in one step and over a parallel rail line in the other.

In each step of the project, one steel cross beam and four longitudinal steel girders had to be put into position. All these lifts followed the same pattern. Due to the space limitations, the Demag CC 3800-1 crane picked up the steel beams – which were up to 54m long and weighed 96-148tonnes – from the SPMT units without a Superlift counterweight.

The crane then slew to a pick-up point to attach the ready-to-go Superlift counterweight frame and its counterweight of 32tonnes to the Demag CC 3800-1 so that the latter would be able to work in bigger radii and, lift the beams to a height of around 22m and then set them down at the intended bridge points. The radii ranged from 40-64m. Due to their length, the beams were rigged to 20m- and 25m-long spreader beams to achieve the required precision for the lifts.

One of the priorities during the project was to minimise its impact on rail traffic, which is why the Wiesbauer team had to perform most of the lifts at night within very tightly defined time when there was no rail traffic. Despite these tight time windows and space conditions, the work was done in five weeks – and all of it including setup, lifting, disassembly, and then moving the crane to the other work area, including the corresponding setup and disassembly after lifting the last steel beam.

Also, outstanding weather conditions worked in the team’s favour, said Wilhelm.

For more information on companies in this article

Related Content

  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • Manitowoc crane helps construct new Illinois bridge
    December 15, 2017
    A barge-mounted crane from Manitowoc is playing a key role in a major Illinois bridge replacement project. The machine is being used by Kraemer North America, which is replacing an 84-year-old truss bridge near Savanna, Illinois. The firm is employing a barge-mounted MLC300 equipped with the sophisticated variable position counterweight (VPC) technology, which is said to allow the MLC300 to adjust its counterweight during each lift and keep the barge stable while lifting. When Manitowoc introduced its VPC
  • Terex wins crane deals in Abu Dhabi and Qatar
    July 28, 2015
    Terex has scored crane deals in both Abu Dhabi and Qatar. Abu Dhabi-based Abu Nasir General Transport has now boosted its equipment fleet with the addition of a Terex AC 100/4L all-terrain crane. The machine joins an existing fleet of Terex cranes with capacities ranging from from 80 to 500tonnes. The company’s operations manager Asif Salim said, “At just 2.55m wide, it’s the most compact machine in its class, which is extremely important when working in confined spaces.” In the 100tonne capacity class an