Steel for Loch Ba bridge

Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
February 6, 2012 Read time: 2 mins
The replacement bridge under construction at Loch Ba in the Scottish Highlands
2327 Allerton Steel, on behalf of 2328 R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland.

R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.

The new composite deck bridge is constructed from weathering grade steel with six plate girders spanning 32m and totalling 55tonnes.

The bridge beams were prefabricated as three pairs landing onto four crosshead beams at the piers, and the bearings at the abutments. The final six-span beams were then placed as individual items.

The structure had site welded splices to allow for transport restrictions en route to the site.

Tom Brodie contracts manager for R J McLeod said: "Allerton has performed well on this job, working with us to deliver the steelwork on time, and I look forward to working with them again".

Paul Robinson, bridges manager for Allerton Steel said: "On my first visit to site there was a foot of snow on the ground and temperatures of -12°C, and due to the remoteness of the site we were concerned. By comparison on the day the bridge was installed the weather was kind to us and our first project with R J McLeod went very well." The scheme will be completed later this year.

Allerton Steel is a specialist fabricator building bridges as well as heavy and complex fabrications. It also works in the commercial building, offshore, oil and gas, nuclear and crane market sectors.

Its main factory is in Northallerton, North Yorkshire and it also has a facility near Durham city, both in north-east England.

For more information on companies in this article

Related Content

  • Bulgaria breaks ground for Martisa River bridge
    August 23, 2023
    The contract was awarded to local engineering firm GBS-Infrastructure Construction in Plovdiv, a subsidiary of the Bulgarian civil engineering group Glavbolgarstroy.
  • Final beam for Gerald Desmond replacement
    June 18, 2020
    The final steel beam has been installed for the replacement Port of Long Beach bridge - California’s first cable-stayed bridge for vehicles.
  • Mexico: underwater tunnel in Latin America
    May 8, 2015
    Mexico will benefit from an important new underwater tunnel - Mauro Nogarin writes. The city of Coatzacoalcos is located at the mouth of the river of the same name, in the Gulf of Mexico, 302km from the city of Salina Cruz, Oaxaca, in the east end of trans-isthmian corridor and at the southern end of Veracruz State. The city is seeing a key development as currently construction is 85% completed on the first immersed tube, underwater tunnel in Latin America. The reasons why experts chose this type of tunne
  • Romanian bridge project well underway
    June 8, 2022
    Romania’s Braila Bridge project is well underway.