Steel for Loch Ba bridge

Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
February 6, 2012 Read time: 2 mins
The replacement bridge under construction at Loch Ba in the Scottish Highlands
2327 Allerton Steel, on behalf of 2328 R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland.

R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.

The new composite deck bridge is constructed from weathering grade steel with six plate girders spanning 32m and totalling 55tonnes.

The bridge beams were prefabricated as three pairs landing onto four crosshead beams at the piers, and the bearings at the abutments. The final six-span beams were then placed as individual items.

The structure had site welded splices to allow for transport restrictions en route to the site.

Tom Brodie contracts manager for R J McLeod said: "Allerton has performed well on this job, working with us to deliver the steelwork on time, and I look forward to working with them again".

Paul Robinson, bridges manager for Allerton Steel said: "On my first visit to site there was a foot of snow on the ground and temperatures of -12°C, and due to the remoteness of the site we were concerned. By comparison on the day the bridge was installed the weather was kind to us and our first project with R J McLeod went very well." The scheme will be completed later this year.

Allerton Steel is a specialist fabricator building bridges as well as heavy and complex fabrications. It also works in the commercial building, offshore, oil and gas, nuclear and crane market sectors.

Its main factory is in Northallerton, North Yorkshire and it also has a facility near Durham city, both in north-east England.

For more information on companies in this article

Related Content

  • Super job for a Demag CC 3800-1 without a Superlift counterweight
    July 4, 2019
    A Demag CC 3800-1 crane with an 84m-long main boom was recently set up in Germany without a Superlift counterweight to save space. The jobsite was the replacement of the old viaduct on the A45 Freeway that spans the Lahn River near Dorlar in Germany. Bietigheim-Bissingen-based crane service provider Wiesbauer solved the site’s space issues by using a Demag CC 3800-1. “This site required us to lift loads of 96-148tonnes at radii of 40-64m, so there was no option but to use a crawler crane in the 650tonne c
  • Work to start on Tyne Bridge refurbishment
    March 11, 2024
    In the UK, Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs.
  • PPRS: the positive side of structural failures
    March 27, 2018
    You learn from your failures, not your successes. That was the overall message for delegates during the day-two morning session on the impact of engineering structural failures. These lessons are also too often “painful”, said Anne-Marie Leclerq, deputy minister for infrastructure within the ministry of transport for the Canadian province of Quebec. On September 30, 2006, a span of the six-lane Concorde Bridge in Laval, near Montreal, collapsed crushing to death five people and injuring six. Only recently
  • Bechtel achieves tricky bridge replacement in tight timeframe
    March 21, 2012
    Contractor Bechtel has worked with Network Rail to complete a major road bridge upgrade in the UK. A construction team worked 104 hours consecutively to replace the bridge, located at Reading Station.