Skip to main content

Steel for Loch Ba bridge

Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
February 6, 2012 Read time: 2 mins
The replacement bridge under construction at Loch Ba in the Scottish Highlands
2327 Allerton Steel, on behalf of 2328 R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland.

R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.

The new composite deck bridge is constructed from weathering grade steel with six plate girders spanning 32m and totalling 55tonnes.

The bridge beams were prefabricated as three pairs landing onto four crosshead beams at the piers, and the bearings at the abutments. The final six-span beams were then placed as individual items.

The structure had site welded splices to allow for transport restrictions en route to the site.

Tom Brodie contracts manager for R J McLeod said: "Allerton has performed well on this job, working with us to deliver the steelwork on time, and I look forward to working with them again".

Paul Robinson, bridges manager for Allerton Steel said: "On my first visit to site there was a foot of snow on the ground and temperatures of -12°C, and due to the remoteness of the site we were concerned. By comparison on the day the bridge was installed the weather was kind to us and our first project with R J McLeod went very well." The scheme will be completed later this year.

Allerton Steel is a specialist fabricator building bridges as well as heavy and complex fabrications. It also works in the commercial building, offshore, oil and gas, nuclear and crane market sectors.

Its main factory is in Northallerton, North Yorkshire and it also has a facility near Durham city, both in north-east England.

For more information on companies in this article

Related Content

  • Crane versatility helps with bridge building
    August 14, 2014
    The versatility and mobility of a Terex crawler crane has helped enormously with the construction of a new road bridge in Luxemburg. The Terex Superlift 3800 lattice boom crawler crane owned by Trier-based Steil Kranarbeiten was used to build a bridge in Luxemburg only two days after the same machine was used on a job in the Hunsrück mountain range. The machine was needed to lift a 440m long bridge across a valley, connecting a new section of highway.
  • World’s largest bridge deck for KAIA expansion
    December 16, 2013
    A bespoke formwork solution from RMD Kwikform is playing a key role in creating the largest ever airport cast bridge deck as part of the multi-billion dollar expansion of King Abdulaziz International Airport near Jeddah, Saudi Arabia. The firm is also a leading player in the creation of arterial tunnels under the airport’s elevated roads, another key part of the project’s first phase works due for completion in 2014. Guy Woodford reports
  • First stay cable installed on UK’s Mersey Gateway bridge
    October 31, 2016
    The first stay cable, 52m long, connecting the Mersey Gateway south pylon to the main bridge deck, has been installed on the Mersey Gateway Project.
  • Peri’s formwork and shoring solution for the “East End Crossing”
    July 6, 2016
    Pylons almost 90m high are a striking feature of a new cable-stayed East End Crossing bridge over the Ohio River in Louisville, Kentucky state in the US The pylons are characterised by their complex shapes and massive legs and cross beams. Peri provided a comprehensive overall concept for its construction – consisting of a planning solution with perfectly matched formwork, climbing, shoring and scaffolding systems along with extensive on-site support. With a Peri solution, the construction crew were a