A 'roller coaster' ride

The Gold Coast region in the Australian state of Queensland is internationally renowned as a tourist area attracting thousands of visitors from Brisbane, where the state's biggest ever road and bridge upgrade project is currently underway. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels: the north is getting a completely new 7km section of motorway on a different alignment to bypass extra traffic, and tolls are being automated to speed flow
July 16, 2012 Read time: 3 mins
The Gold Coast region in the Australian state of Queensland is internationally renowned as a tourist area attracting thousands of visitors from Brisbane, where the state's biggest ever road and bridge upgrade project is currently underway.

Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels: the north is getting a completely new 7km section of motorway on a different alignment to bypass extra traffic, and tolls are being automated to speed flows.

At the heart of the project is a duplication of the 1.63km long Gateway Bridge, with its slim central soaring concrete arch, which was a world record holder in its time for a concrete box balanced cantilever bridge. The 260m long main span carrying three lanes of traffic each way, nearly 65m above the river, is still the biggest hollow concrete box construction anywhere.

The AU$1.88 billion (US$1.5 billion) Brisbane Gateway Upgrade Project in the state capital will help alleviate traffic congestion in the area and improve the vital link to the Gold Coast.

"The upgrade project will deliver many benefits to Queensland, including safer, quicker and easier travel on the Gateway Motorway; better connections for business, industry and tourism, and an overall improved situation for motorists, cyclists and pedestrians," says Jeremy Shaw, Conplant client services manager, the Australian distributor of Ammann products (some 40 Ammann rollers are in use on the project), which hired out all the machines on the south side of the project.
"The majority of the rollers on this site are Ammann products, ranging from
1-27tonne vibrating smooth and pad drum rollers, and are equipped with ROPS2 anti-roll technology.

"Worksites on the south side feature some very steep batters and abutments, so the ROPS2 technology is an excellent safety net, particularly for less experienced operators. There is next to no possibility of a rollover as long as the operator is following proper procedure, and there have been no rollover incidents on this project."

ROPS2 is a two-stage system that first alerts the operator with an audible alarm when a pre-determined gradient is reached, then shuts down the vibration if the machine continues to tilt, and was introduced to the Australian market in 2007.

Related Content

  • Indra chooses Citilog for Silvertown Tunnel
    June 28, 2024
    Citilog will integrate its automatic incident detection (AID) system to help reduce congestion in and around the tunnel between the London borough of Greenwich, the peninsula area, and West Silvertown.
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.
  • Brisbane’s new airport link is an engineering success
    April 12, 2013
    Financial troubles for Brisbane's new Airport Link overshadow its construction success – Adrian Greeman writes. Political argument and legal dispute is likely to rage for some time yet over the bankruptcy of Australian road operator BrisConnect, which went into receivership this February with A$3 billion in debt. Toll paying users for its new Airport Link have been less than half the predicted numbers since it opened in July last summer. But if its nancial engineering is being questioned, the same is not t
  • Liebherr’s truck-mounted 37 Z4 XXT concrete pump
    February 19, 2015
    A truck-mounted concrete pump configured in four sections, Liebherr’s 37 Z4 XXT’s 37m distributor boom in Z-fold design is said to be extremely torsion resistant, and consequently exhibits low-vibration boom movements on the building site. The concrete pipeline on the 37 Z4 XXT is configured close to the boom on the left and right-hand sides, guaranteeing a balanced weight distribution. The pipe bends of the concrete pipeline feature a large radius of 27.5cm ensuring minimal losses in pressure over the le