Record breaking ABM bridge beams installed near Raith, Scotland

One of the largest mobile cranes in the UK, a 1,500tonne capacity unit, recently positioned nine 90tonne 42m pre-stressed bridge beams by ABM Precast Solutions. The massive W-beams were hoisted into place at Junction 5, the Raith Interchange, on Scotland’s M74 motorway – part of the M8-M73-M74 motorway improvements project.
September 30, 2016 Read time: 2 mins
Up, up and away for ABM's W-beams

One of the largest mobile cranes in the UK, a 1,500tonne capacity unit, recently positioned nine 90tonne 42m pre-stressed bridge beams by 8508 ABM Precast Solutions.

The massive W-beams were hoisted into place at Junction 5, the Raith Interchange, on Scotland’s M74 motorway – part of the M8-M73-M74 motorway improvements project.

The Raith interchange is a noted pinch point in the Scottish motorway system, so installation took place in three night operations from midnight to four in the morning. The W-beams are among the largest bridge beams of this type fabricated in the UK in recent years. ABM are supplying precast structures to six other bridges on the £500 million project being delivered for Scottish Roads Partnership on behalf of Transport Scotland.

The beams were also the largest pre-stressed beams produced by ABM since a major upgrading of the company’s factory in the mid-England village of Tuxford.

Each W-beam was cast in purpose-built heated moulds ensuring rapid uniform curing to achieve the 50N/m2 stress load transfer strength. Each beam has more than a 1,700tonnes pre-stress load.

The loads were carried by Walker Haulage of Tuxford to the Scottish border - without escort.  Local police then escorted the steering bogie trailers to site to complete the near-420km journey.

For more information on companies in this article

Related Content

  • Balfour Beatty demolishes Scottish M8 bridge to create junction
    July 11, 2013
    Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
  • Liebherr launches rough terrain cranes LRT 1090-2.1 and 1100-2.1
    March 7, 2017
    Liebherr announced at the CONEXPO-CON/AGG exhibition in Las Vegas that the company is back in the rough terrain crane market after a 30-year absence. The Swiss-based company is focusing on the North American market with the launch of two mobile crane models, said Daniel Pitzer, head of Liebherr USA.
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo