Record breaking ABM bridge beams installed near Raith, Scotland

One of the largest mobile cranes in the UK, a 1,500tonne capacity unit, recently positioned nine 90tonne 42m pre-stressed bridge beams by ABM Precast Solutions. The massive W-beams were hoisted into place at Junction 5, the Raith Interchange, on Scotland’s M74 motorway – part of the M8-M73-M74 motorway improvements project.
September 30, 2016 Read time: 2 mins
Up, up and away for ABM's W-beams

One of the largest mobile cranes in the UK, a 1,500tonne capacity unit, recently positioned nine 90tonne 42m pre-stressed bridge beams by 8508 ABM Precast Solutions.

The massive W-beams were hoisted into place at Junction 5, the Raith Interchange, on Scotland’s M74 motorway – part of the M8-M73-M74 motorway improvements project.

The Raith interchange is a noted pinch point in the Scottish motorway system, so installation took place in three night operations from midnight to four in the morning. The W-beams are among the largest bridge beams of this type fabricated in the UK in recent years. ABM are supplying precast structures to six other bridges on the £500 million project being delivered for Scottish Roads Partnership on behalf of Transport Scotland.

The beams were also the largest pre-stressed beams produced by ABM since a major upgrading of the company’s factory in the mid-England village of Tuxford.

Each W-beam was cast in purpose-built heated moulds ensuring rapid uniform curing to achieve the 50N/m2 stress load transfer strength. Each beam has more than a 1,700tonnes pre-stress load.

The loads were carried by Walker Haulage of Tuxford to the Scottish border - without escort.  Local police then escorted the steering bogie trailers to site to complete the near-420km journey.

For more information on companies in this article

Related Content

  • New bridge refurbishment solutions now available
    July 15, 2015
    An array of new bridge refurbishment and repair solutions are available – Mike Woof writes Around the world there are many bridges requiring repairs or refurbishment, and there is a ready market for novel solutions to upgrade existing structures. New developments offer quicker and more efficient ways to improve bridge surfaces and structural performance and add new life to ageing designs. Spancrete is broadening the availability of its novel precast building solutions worldwide by offering these to th
  • Jobs lost at ailing Cleveland Bridge
    August 6, 2021
    The steel fabricator in Darlington, England, is now up for sale.
  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • New concrete barrier on key M5 motorway section
    October 30, 2012
    Contractor Tarmac has carried out major works on the UK’s M5 motorway after recycling around 30,000tonnes of concrete and providing 8,000m3 of new concrete for new slip-form central barrier works. The project, between Junctions 3 and 4a of the M5, was delivered as part of an eight-week scheme to install 13km of new concrete safety barrier. Approximately 30,000 tonnes of concrete were excavated and then crushed into Type 1 and 6F5 aggregates at Tarmac’s recycling site in Ettingshall, Wolverhampton. Over 14,0